  Key Facts & Figures

 
A Deputy General Manager (DGM) heads the Eastern RSC with the support of an Assistant General Manager (AGM). Operations and Maintenance (O&M) activities are divided into three regions namely Ampara, Batticaloa and Akkaraipattu Region and are managed by three different regional managers. Mainly the RSC functions are to provide necessary support to the three regional offices in the day to day O&M activities and to provide help and guidance in the existing scheme rehabilitation and augmentation work.

All O&M managers report to the DGM through the AGM and all RSC functions are monitored by the Additional General Manager. The RSC provides services to all regional offices within their capacity, any additional help is obtained from the head office (HO) through the Additional General Manager.

Inspite of having functioned for a long time, the RSC still lacks capacity specially in some technical services, such as planning and design activities, electromechanical works etc. This is primarily due to lack of technical staff and other resources. The main reasons for the shortage of staff are the geographical location and the past conflict situation which has made it very difficult for the RSC to appoint the required skilled personnel as only a few are willing to come and work in the area.
 

1. Location of the Area
                     
 
  Statistics of the Area
    Total Area 9,996.0 km2
    Population (2007) 1,460,393
    Population (2009)* 1,539,000
    Population Density (2009) 154.0/km2
    * Estimated mid year Population by the Department of Census and Statistics - Sri Lanka
             
             
 
    Please click on map to enlarge it.
   
     
       

  Ampara District Map   Click here to View or Download the original map published by the Survey Department of the Government of Sri Lanka.

  Batticaloa District Map   Click here to View or Download the original map published by the Survey Department of the Government of Sri Lanka.

  Trincomalee District Map   Click here to View or Download the original map published by the Survey Department of the Government of Sri Lanka.

Index ^                  

2. Comparison of Service Connections
 
As at end of
No. of Connection
 
2006
49,313
 
2007
54,997
 
2008
74,942
 
2009
85,061
 
         
         
         
         
         
         
         
         
         
         
Index ^      

3. Details of Schemes within the area
 
  The quality of water being supplied is tested regularly. Click here for a summary of test results taken island-wide.  
 
3.1 Schemes which are presently in operation
  Region Scheme
Total no. of connections as end of 31st December 2009
Average Monthly Production (m3/ month)
     
1
Ampara District Damana
282
6,276
     
2
Uhana
1,160
20,933
     
3
Mahaoya
68
3,325
     
4
Batticalao
1,780
58,647
     
5
Ampara
6,810
230,093
     
6
Kathankudy
378
4,253
     
7
Padiyathalawa
384
8,284
     
8
Inginiyagala
329
8,228
     
9
Dehiattakandiya
935
25,094
     
10
Sammanthurai
8,000
166,445
     
11
Kallar
3,606
35,923
     
12
Akkaraipattu Ninthavur
2,032
289,466
     
13
Karaithivu
3,199
     
14
Sainthamaruthu
5,443
     
15
Kalmunai
8,256
     
16
Maruthamunai
3,508
     
17
Irakkamam
1,739
128,839
     
18
Akkaraipattu
3,931
     
19
Addalaichenai
1,699
     
20
Oluvil & Palamunai
2,062
     
21
Pottuvil
412
5,878
     
22
Nivithanveli
-
-
     
23
Trincomalee District Trincomalee
28,974
834,117
     
24
Seruwila
70
2,477
     
25
Sampoor
These Schemes are now integrated with other Schemes
     
26
Kantale      
27
Palaiyoothu      
28
Thampalagamam      
29
Kinniya      
30
Andakulam      
Total
85,057
1,828,278
     
Index ^                  
3.2 Ongoing Projects
3.2.1 Small and Medium Water Supply Projects
  Project Name
No. of Beneficiaries
Total Cost Estimate (Rs. Million)
Duration
   
From
To
1
Kantale (Agbopura) Water Supply
25,000
274.8
January 1999
2010
   
2
Thampalakamam Water Supply
30,000
95.2
January 1999
2010
   
3
Serunuwara Water Supply
5,000
110.1
January 2001
2010
   
 
   
3.2.2 Large Scale Water Supply and Sanitation Projects
  Project Name (Donor)
No. of Beneficiaries
Total Cost Estimate (Rs. Million)
Duration
   
From
To
   
1
Eastern Coastal Towns of Ampara District (ECTAD) Water Supply Phase II (Australia)
161,400
10,914.0
October 2002
2010
   
2
Balance Distribution Expansions in Ampara District (JBIC)
267,000
-
2009
2011
   
Inter-Provincial Projects    
3
Secondary Towns Rural Community Based Water Supply & Sanitation (ADB 4th Project)
968,000 (Water) & 171,500 (Sanitation)
19,272.0
2004
2110
   
4
Augmentation of Nawalapitiya, Ampara and Koggala Water Supply (KfW German)
86,000
2,700.0
January 2001
2010
   
               
Index ^            

4. Contact Details
  Postal Address Regional Support Centre (Eastern)
National Water Supply & Drainage Board
42, Vipulananda Avenue,
Kalladi,
Batticoloa
       
  Telephone/ Fax +94 65 2227476        
                       
  Deputy General Manager        
  Name Mr. M. I. A. Lathieff        
  Mobile +94 77 7773525        
  E-mail dgmeast@waterboard.lk        
                       
  Assistant General Manager (Eastern)        
  Name Mr. W. G. A. Nandasiri        
  Telephone +94 63 2224979        
  Fax +94 63 2223926        
  Mobile +94 77 2240571        
  E-mail agmeast@waterboard.lk        
                       
  Managers (Operational & Maintenance)        
  Trincomalee          
  Name Mr. S. M. M. Ilyas        
  Telephone/ Fax +94 26 2234283
       
  Mobile +94 77 3179440        
  E-mail managertrinco@waterboard.lk        
  Responsibility Areas Trincomalee, Palaiyoothu, Andakulam, Kinniya, Thampalagamam, Kanthale  
                       
  Ampara          
  Name Mr. J. N. Careem        
  Telephone +94 63 2222125
       
  Fax +94 63 2222024        
  Mobile +94 77 7864445        
  E-mail manageramp@waterboard.lk        
  Responsibility Areas Uhana, Inginiyagala, Damana, Hingurana, Padiyathalawa, Batticaloa, Kattankudy, Ampara, Kallar, Mahaoya  
       
  Akkaraipattu          
  Name Mr. I. L. Hyder Ali        
  Telephone/ Fax +94 67 2277339
       
  Mobile +94 77 2442047        
  E-mail managerakp@waterboard.lk        
  Responsibility Areas Irakkamam, Akkaraipattu, Addalachchenai, Palmunia, Oluvil, Ninthavur, Karaithivu, Sainthamaruthu, Kalmunai, Maruthamunai, Thirukkovil, Pttovul  
           
Index ^          

5. Key Facts and Figures
                       
5.1 Service Standard Indicators
Service Indicators
RSC (Eastern) 2008
       
Regional Average
       
Water Coverage (%) Pipe System maintained by NWSDB
23.9%
       
Per Capita Consumption (l/c/d)
79.7
       
Water Availability (hours)
10.9
       
Water Quality - Bacteriological Quality Compliance
96.2%
       
Water Quality - Bacteriological Testing Compliance
100.0%
       
Water Quality - All Samples Compliance
88.8%
       
Sewerage Coverage (%)
-
       
           
5.2 Operational Indicators    
Operational Indicators
RSC (Eastern) 2008
       
Regional Average
       
Non-Revenue Water (%)
32.9%
       
Non-Revenue Water - m3/conn/day
0.27
       
Defective Meters per '000 connections
29
       
Total Staff/ 1000 connection
11
       
Operational Staff/ 1000 connection
10
       
Estimated Bills/ 1000 connections
89
       
                       
5.3 Performance in Customer Service    
Customer Service Indicators
RSC (Eastern) 2008
       
Regional Average
       
Response to requests for new service connections (%)
62.2%
       
Customer Complaints Volume (Complaints/ 1000 connection)
7.1
       
Customer Complaints Resolution
81.4%
       
                       
5.4 Key Performance Indicators (KPIs)    
Financial KPIs
RSC (Eastern) 2008
       
Regional Average
       
Collection Ratio (%)
97.1%
       
Accounts Receivable Period (months)
4.2
       
Collectable Accounts Receivable Period (months)
2.6
       
Operating Ratio
1.57
       
Production Cost (LKR/ m3 Produced)
25.35
       
Average Tariff (LKR/ m3 Sold)
15.59
       
Stock Efficiency (LKR/ connection)
2,528
       

Index ^
 
All Island toll free Call Centre
for seeking
information of our activities or for any complaints to the NWSDB on breakdowns, interruptions and water leaks.
Call 1939
 
::: Updated on 2010.03.18 :::
                     
© 2010 National Water Supply and Drainage Board. All rights reserved.