Projects & Technical Capabilities Tsunami Projects
 
      Untitled Document
Tsunami Affected Area Water Supply & Sanitation Projects (On-going)
               
No.
Project Name
District
No. of Beneficiaries
Duration
Total Estimated Cost (Rs. million)
Actual Expenditure up to 2008.12.31 (Rs. '000s)
From
To
1
UNICEF Funded Tsunami Mulaitivu, Ampara, Hambantota, Kalutara, Tangalle & Thirukkovil
2005
2010
3,100.0
3,412,790

2
ADB/ TAARF Funded Tsunami
(Tsunami Affected Areas Rebuilding Fund)
Trincomalee, Batticaloa & Hambantota
14,253 families
2005
2010
1,220.0
486,580

3
KfW Funded Tsunami (Ambalangoda) Galle  
2005
2010
3,379.3
2,983,000

4
French Funded Tsunami (AFD) Trincomalee  
2006
2010
1,776.0
66,890

5
IFRC Funded Tsunami Jaffna, Ampara, Hambantota, Matara & Galle  
2005
2010
3,785.0
699,000

6
USAID Funded Tsunami (Pottuvil) Ampara  
2005
2010
895.0
884,380

7
Greater Trincomalee Integrated Water Supply (France) Trincomalee  
2006
2010
2,645.0
101,460

       
   

Abbreviations:
ADB - Asian Development Bank
IFRC - International Federation of Red Cross
KfW - Reconstruction Credit Institute
UNICEF - United Nations International Children's Fund
USAID - United States Agency for International Development

         
               
::: Updated on 2010.04.27 :::
               