| Tsunami Affected Area Water Supply & Sanitation Projects (On-going) |
| |
|
|
|
|
|
|
|
No. |
Project Name |
District |
No. of Beneficiaries |
Duration |
Total Estimated Cost (Rs. million) |
Actual Expenditure up to 2008.12.31 (Rs. '000s) |
From |
To |
1 |
UNICEF Funded Tsunami |
Mulaitivu, Ampara, Hambantota, Kalutara, Tangalle & Thirukkovil |
|
2005 |
2010 |
3,100.0 |
3,412,790 |
|
2 |
ADB/ TAARF Funded Tsunami
(Tsunami Affected Areas Rebuilding Fund) |
Trincomalee, Batticaloa & Hambantota |
14,253 families |
2005 |
2010 |
1,220.0 |
486,580 |
|
3 |
KfW Funded Tsunami (Ambalangoda) |
Galle |
|
2005 |
2010 |
3,379.3 |
2,983,000 |
|
4 |
French Funded Tsunami (AFD) |
Trincomalee |
|
2006 |
2010 |
1,776.0 |
66,890 |
|
5 |
IFRC Funded Tsunami |
Jaffna, Ampara, Hambantota, Matara & Galle |
|
2005 |
2010 |
3,785.0 |
699,000 |
|
6 |
USAID Funded Tsunami (Pottuvil) |
Ampara |
|
2005 |
2010 |
895.0 |
884,380 |
|
7 |
Greater Trincomalee Integrated Water Supply (France) |
Trincomalee |
|
2006 |
2010 |
2,645.0 |
101,460 |
|
| |
|
|
|
|
|
|
|
Abbreviations:
ADB - Asian Development Bank
IFRC - International Federation of Red Cross
KfW - Reconstruction Credit Institute
UNICEF - United Nations International Children's Fund
USAID - United States Agency for International Development
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
| ::: Updated on 2010.04.27 ::: |
| |
|
|
|
|
|
|
|