Most of the Development Activities of the region are carried out by the Construction Section of the region .

 CONSTRUCTION SECTION ( RSC WS )

Objective of Construction Section

Construction section is responsible for all the activities in relation to construction works and contract administration. The Construction Section plays a major role in the Regional Support Centre, which covers the three Operation & Maintenance (O&M) regions named Dehiwala, Panadura- Horana and Kalutara.

Key Functions of the section

Responsible for the major construction work within the RSC limits.

      After the award of contracts, arrange the pre –construction meeting and give the kick-start for the work undertaken by the Contractor. 

Carry out the construction activities as per the contract.

Liaison with Road Authorities and other Institutions. 

Supervise the works to ensure that they are carried out in accordance with the specifications and other related conditions.

Facilitate the contractor to carry out the works and coordinate all the stake holders involved in the works.

Check the contractors’ monthly payment applications and certify them for the payments (as per the checklist).

Valuation of variations and obtaining necessary VO committee approval for the payments accordingly.

Give site instructions to the Contractor according the changes arises time to time. Take over the completed works.

Issue taking over certificate, substantial completion certificate and completion certificate.

Check the final bill and certify the payment as per the contract condition.

Prepare duly signed fixed asset Forms & handover to Finance Division

Check and certify “As built drawings”.

Reconciliation of the materials and update. 

 

ONGOING & RECENTLY COMPLETED DEVELOPMENT ACTIVITIES - 2021 First QTR

   

Item No.

Project

Contract No.

Contractor

Contract Amount (Mn)

Expected Completion date

Paid up to 31.12.2018

Paid in 2019

Bills in Hand at

Balance Fund req'd in 2019 (Mn)

Approved Allocation for 2019 in Rev-3 (Mn)

Physical Progress as at March 2021

Remarks

Finance

Const. Div.

REHABILITATION PROJECTS

1

Excavation, Laying & Backfilling of 225mm, 160mm, 90mm dia. UPVC pipes & other works along Horana - Ingiriya road Wagawatta to Ingiriya at Horana WSS in Panadura - Horana Region

2017/25

M/s. Brians Engineering (Pvt) Ltd

25.45

Completed in 2020

7.77

7.79

6.19

3.00

9.19

6.00

100.0%

83.0%

Final Payment Certifcate to be prepared after the construction of AV chamber at Ingiriya Town

2

Excavation, Laying & Backfilling of 160mm, 90mm dia & 63mm dia. uPVC pipes & other works along Horana - Padukka Road near Owitiyagala Road Junction to Kananwila Pradeshiya Sabha at Horana WSS in Panadura- Horana Region

2017/57

M/s. Brians Engineering (Pvt) Ltd

6.63

Completed in 2019

1.33

1.87

2.56

1.00

2.56

5.20

100.0%

87.0%

Final Payment Certifcate to be prepared after the interconnection through culvert

3

Laying of DI Pipes, Fittings , Specials and Valves for Culvert Crossing & Bridge Crossings along Ingiriya- Meepe Road

2017/85

M/s. Ravindu Engineeing & Construction

2.59

Completed in 2020

0.00

0.00

0.00

0.00

0.30

0.60

100.0%

0.0%

Slow progress due to rain

4

Construction of Drive Through Building and Meter Readers' room for Area Engineer (Moratuwa) office

2018/43

M/s. Karawgoda Construction

6.82

Completed in 2020

1.37

1.89

0.00

0.00

1.50

7.50

100.0%

37.0%

 

5

Supply & Placing of Filter Media for slow sand fillter at Mathugama

2018/34

M/s. R.A.Building Materiel Suppliers

3.79

1st Filter Completed in 2020

0.69

0.00

0.00

0.00

0.80

0.50

50.0%

0.0%

 

6

Construction of Soysapura Pump House at Dehiwala/Moratuwa Region

2018/95

M/s. Solanma Engineering (Pvt) Ltd

12.80

Completed in 2020

0.00

4.85

2.20

0.00

3.70

8.20

100.0%

64.0%

 

7

Laying of uPVC and DI pipes, Specials, DI valves and accessories for Raigampura Green Industrial and Techno Development Zone (Stage III)

 

M/s. Dumindu Constructions & Company

16.17

Completed in 2021

           

100.0%

   

8

Bid for Construction of 1st Floor of OIC Office at Piliminawatta for Mathugama/Piliminawatta/Bombuwala Water Supply Scheme

 

M/s. Athukorala Construction

6.90

Completed in 2021

           

100.0%

   

NRW PROJECTS

   

9

Renovation of Beruwala Reservoir (Building & Civil Works)

2018/59

M/s. Finex Engineering (Pvt) Ltd

29.40

Completed

0.00

11.10

0.00

3.00

3.00

14.00

100.0%

   

10

Renovation of Maggona Tower

2017/86

M/s. Finco Engineering

9.98

Completed

3.75

1.57

0.00

0.60

0.60

2.57

100.0%

   

11

Tender for Renovation of Ground Reservoir at Alwis Place in Kalutara

 

M/s. Finex Engineering (Pvt) Ltd

74.19

Feb-21

           

60.0%

   

UTILITY SHIFTING PROJECTS

12

Laying of uPVC, PE and DI pipes, specials, DI Valves and Accessories for Kawdana Attidiya Road

2017/ 99R-02

M/s. Ceyoka Enginnering (Pvt)Ltd

5.00

Completed in 2020

0.00

2.85

0.61

0.00

0.61

5.00

100.0%

57.0%

 

13

Laying of 160mm uPVC & DI Pipes special , valves and Construction of Chambers of proposed pipe line (5.2km) for Wadduwa Moronthuduwa Road under NWSDB funds - Stage-I

2018/40

M/s. MAGA Engineering

7.12

Completed in 2020

0.00

3.96

0.00

1.63

2.00

17.60

100.0%

56.0%

IPC-3 (Rs. 1.63 Million) prepared

14

Laying of 160mm Upvc &DI Pipes special ,valves and Construction of Chambers of proposed pipe line (5.2km) for Wadduwa Moronthuduwa Road under NWSDB funds - Stage II

2018/41

M/s. MAGA Engineering

7.46

Completed in 2020

0.00

2.11

0.00

0.00

1.50

100.0%

31.0%

 

15

Laying of DI/ uPVC Pipes for Hill Street towards Nadimala Junction up to Bellantota Junction under Dehiwala Region

2016/122

M/s. SD &CC

71.54

Completed in 2019

12.57

0.00

0.00

(1.54)

(1.54)

0.00

100.0%

114.0%

Final Bill to be Prepared

RECHARGEABLE FUNDED PROJECTS

 

16

Laying of 225mm dia.uPVC and DI pipes, Specials & Valves for Millaniya Industrial Zone - Stage I

2017/89

M/s. C&C Engineering (Pvt) Ltd

37.47

Completed in 2020

10.74

6.54

0.00

1.00

1.00

99.0%

100.0%

Flushing & Disinfection, Marker Posts to be completed

 

17

Supply & Laying of water transmission main at Wagawatta Industrial Zone

2016/10/02.004

M/s. SAW Engineering (Pvt) ltd

52.89

Completed in 2019

41.43

   

0.00

100.0%

100.0%

Only the Supervision is done by NWSDB

 

18

Laying of uPVC and DI pipes, Specials, DI valves and accessories for Water Supply to CGR Quarters Ratmalana

 

M/s. Lakshieka Construction

24.95

Sep-21

           

7.0%

   

19

Laying of uPVC and DI pipes, Specials, DI valves and accessories for 225mm dia. uPVC pipeline for Anguruwattota road - Raigamapura Green Industrial and Techno Development Zone (Stage-1)

2018/89

M/s. Brians Engineers (Pvt) ltd

28.90

Apr-21

0.00

0.00

0.00

0.00

0.00

0.0%

92.0%

   

20

Laying of uPVC and DI pipes, Specials, DI valves and accessories for Raigampura Green Industrial and Techno Development Zone (Stage II)

 

M/s. Brians Engineers (Pvt) ltd

18.89

Apr-21

           

92.0%

   

GRANT/FUNDED BY OTHER INSTITUTIONS/PROJECT FUND

21

Kesbewa- Pokunuwita Road pipe laying (Kahatuduwa Interchange to Pokunuwita Junction)

RDA/SRCP/JCB/ADB/CP-02

M/s. MAGA Engineering

RDA Awarded Contract

Completed in 2020

       

0.00

100.0%

100.0%

Only the Supervision is done by NWSDB

 

22

Gonapola - Pokunuwita Road pipe laying

 

M/s. MAGA Engineering

RDA Awarded Contract

Dec-21

           

25.0%

   

23

Rehabilitation & Improvements to Cross Junction to Digarolla Bridge

RDA

M/s. Solanma Engineering (Pvt) Ltd

RDA Awarded Contract

Completed in 2020

       

0.00

100.0%

100.0%

Only the Supervision is done by NWSDB

 

24

Construction of Pipeline Installation and Leak DetectionTraining Yard

 

JICA

USD 43,580.20 plus Rs.33,57 Mn

Completed in 2020

           

100.0%

   

25

Construction of OIC Office for Horana OIC

 

AMAIWSP

AMAIWS Project Funded

Mar-21

           

25%

   

26

Tender for Construction of 500m3 Capacity Ground Reservoir and Pump House for Dahampahangama Water Supply Scheme

 

M/s Kandy Construction

AMAIWS Project Funded (32.95 Mn)

May-21

           

60%

   

27

Renovation of Regional Manager Office, Kalutara

 

Southern Construction

AMAIWS Project Funded (7.60 Mn)

May-21

           

25%