Most of the Development Activities of the region are carried out by the Construction Section of the region .
CONSTRUCTION SECTION ( RSC WS )
Objective of Construction Section
Construction section is responsible for all the activities in relation to construction works and contract administration. The Construction Section plays a major role in the Regional Support Centre, which covers the three Operation & Maintenance (O&M) regions named Dehiwala, Panadura- Horana and Kalutara.
Key Functions of the section
Responsible for the major construction work within the RSC limits.
After the award of contracts, arrange the pre –construction meeting and give the kick-start for the work undertaken by the Contractor.
Carry out the construction activities as per the contract. |
Liaison with Road Authorities and other Institutions. |
Supervise the works to ensure that they are carried out in accordance with the specifications and other related conditions. |
Facilitate the contractor to carry out the works and coordinate all the stake holders involved in the works. |
Check the contractors’ monthly payment applications and certify them for the payments (as per the checklist). |
Valuation of variations and obtaining necessary VO committee approval for the payments accordingly. |
Give site instructions to the Contractor according the changes arises time to time. Take over the completed works. |
Issue taking over certificate, substantial completion certificate and completion certificate. |
Check the final bill and certify the payment as per the contract condition. |
Prepare duly signed fixed asset Forms & handover to Finance Division |
Check and certify “As built drawings”. |
Reconciliation of the materials and update.
|
ONGOING & RECENTLY COMPLETED DEVELOPMENT ACTIVITIES - 2021 First QTR |
|||||||||||||||||
Item No. |
Project |
Contract No. |
Contractor |
Contract Amount (Mn) |
Expected Completion date |
Paid up to 31.12.2018 |
Paid in 2019 |
Bills in Hand at |
Balance Fund req'd in 2019 (Mn) |
Approved Allocation for 2019 in Rev-3 (Mn) |
Physical Progress as at March 2021 |
Remarks |
|||||
Finance |
Const. Div. |
||||||||||||||||
REHABILITATION PROJECTS |
|||||||||||||||||
1 |
Excavation, Laying & Backfilling of 225mm, 160mm, 90mm dia. UPVC pipes & other works along Horana - Ingiriya road Wagawatta to Ingiriya at Horana WSS in Panadura - Horana Region |
2017/25 |
M/s. Brians Engineering (Pvt) Ltd |
25.45 |
Completed in 2020 |
7.77 |
7.79 |
6.19 |
3.00 |
9.19 |
6.00 |
100.0% |
83.0% |
Final Payment Certifcate to be prepared after the construction of AV chamber at Ingiriya Town |
|||
2 |
Excavation, Laying & Backfilling of 160mm, 90mm dia & 63mm dia. uPVC pipes & other works along Horana - Padukka Road near Owitiyagala Road Junction to Kananwila Pradeshiya Sabha at Horana WSS in Panadura- Horana Region |
2017/57 |
M/s. Brians Engineering (Pvt) Ltd |
6.63 |
Completed in 2019 |
1.33 |
1.87 |
2.56 |
1.00 |
2.56 |
5.20 |
100.0% |
87.0% |
Final Payment Certifcate to be prepared after the interconnection through culvert |
|||
3 |
Laying of DI Pipes, Fittings , Specials and Valves for Culvert Crossing & Bridge Crossings along Ingiriya- Meepe Road |
2017/85 |
M/s. Ravindu Engineeing & Construction |
2.59 |
Completed in 2020 |
0.00 |
0.00 |
0.00 |
0.00 |
0.30 |
0.60 |
100.0% |
0.0% |
Slow progress due to rain |
|||
4 |
Construction of Drive Through Building and Meter Readers' room for Area Engineer (Moratuwa) office |
2018/43 |
M/s. Karawgoda Construction |
6.82 |
Completed in 2020 |
1.37 |
1.89 |
0.00 |
0.00 |
1.50 |
7.50 |
100.0% |
37.0% |
||||
5 |
Supply & Placing of Filter Media for slow sand fillter at Mathugama |
2018/34 |
M/s. R.A.Building Materiel Suppliers |
3.79 |
1st Filter Completed in 2020 |
0.69 |
0.00 |
0.00 |
0.00 |
0.80 |
0.50 |
50.0% |
0.0% |
||||
6 |
Construction of Soysapura Pump House at Dehiwala/Moratuwa Region |
2018/95 |
M/s. Solanma Engineering (Pvt) Ltd |
12.80 |
Completed in 2020 |
0.00 |
4.85 |
2.20 |
0.00 |
3.70 |
8.20 |
100.0% |
64.0% |
||||
7 |
Laying of uPVC and DI pipes, Specials, DI valves and accessories for Raigampura Green Industrial and Techno Development Zone (Stage III) |
M/s. Dumindu Constructions & Company |
16.17 |
Completed in 2021 |
100.0% |
||||||||||||
8 |
Bid for Construction of 1st Floor of OIC Office at Piliminawatta for Mathugama/Piliminawatta/Bombuwala Water Supply Scheme |
M/s. Athukorala Construction |
6.90 |
Completed in 2021 |
100.0% |
||||||||||||
NRW PROJECTS |
|||||||||||||||||
9 |
Renovation of Beruwala Reservoir (Building & Civil Works) |
2018/59 |
M/s. Finex Engineering (Pvt) Ltd |
29.40 |
Completed |
0.00 |
11.10 |
0.00 |
3.00 |
3.00 |
14.00 |
100.0% |
|||||
10 |
Renovation of Maggona Tower |
2017/86 |
M/s. Finco Engineering |
9.98 |
Completed |
3.75 |
1.57 |
0.00 |
0.60 |
0.60 |
2.57 |
100.0% |
|||||
11 |
Tender for Renovation of Ground Reservoir at Alwis Place in Kalutara |
M/s. Finex Engineering (Pvt) Ltd |
74.19 |
Feb-21 |
60.0% |
||||||||||||
UTILITY SHIFTING PROJECTS |
|||||||||||||||||
12 |
Laying of uPVC, PE and DI pipes, specials, DI Valves and Accessories for Kawdana Attidiya Road |
2017/ 99R-02 |
M/s. Ceyoka Enginnering (Pvt)Ltd |
5.00 |
Completed in 2020 |
0.00 |
2.85 |
0.61 |
0.00 |
0.61 |
5.00 |
100.0% |
57.0% |
||||
13 |
Laying of 160mm uPVC & DI Pipes special , valves and Construction of Chambers of proposed pipe line (5.2km) for Wadduwa Moronthuduwa Road under NWSDB funds - Stage-I |
2018/40 |
M/s. MAGA Engineering |
7.12 |
Completed in 2020 |
0.00 |
3.96 |
0.00 |
1.63 |
2.00 |
17.60 |
100.0% |
56.0% |
IPC-3 (Rs. 1.63 Million) prepared |
|||
14 |
Laying of 160mm Upvc &DI Pipes special ,valves and Construction of Chambers of proposed pipe line (5.2km) for Wadduwa Moronthuduwa Road under NWSDB funds - Stage II |
2018/41 |
M/s. MAGA Engineering |
7.46 |
Completed in 2020 |
0.00 |
2.11 |
0.00 |
0.00 |
1.50 |
100.0% |
31.0% |
|||||
15 |
Laying of DI/ uPVC Pipes for Hill Street towards Nadimala Junction up to Bellantota Junction under Dehiwala Region |
2016/122 |
M/s. SD &CC |
71.54 |
Completed in 2019 |
12.57 |
0.00 |
0.00 |
(1.54) |
(1.54) |
0.00 |
100.0% |
114.0% |
Final Bill to be Prepared |
|||
RECHARGEABLE FUNDED PROJECTS |
|||||||||||||||||
16 |
Laying of 225mm dia.uPVC and DI pipes, Specials & Valves for Millaniya Industrial Zone - Stage I |
2017/89 |
M/s. C&C Engineering (Pvt) Ltd |
37.47 |
Completed in 2020 |
10.74 |
6.54 |
0.00 |
1.00 |
1.00 |
99.0% |
100.0% |
Flushing & Disinfection, Marker Posts to be completed |
||||
17 |
Supply & Laying of water transmission main at Wagawatta Industrial Zone |
2016/10/02.004 |
M/s. SAW Engineering (Pvt) ltd |
52.89 |
Completed in 2019 |
41.43 |
0.00 |
100.0% |
100.0% |
Only the Supervision is done by NWSDB |
|||||||
18 |
Laying of uPVC and DI pipes, Specials, DI valves and accessories for Water Supply to CGR Quarters Ratmalana |
M/s. Lakshieka Construction |
24.95 |
Sep-21 |
7.0% |
||||||||||||
19 |
Laying of uPVC and DI pipes, Specials, DI valves and accessories for 225mm dia. uPVC pipeline for Anguruwattota road - Raigamapura Green Industrial and Techno Development Zone (Stage-1) |
2018/89 |
M/s. Brians Engineers (Pvt) ltd |
28.90 |
Apr-21 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.0% |
92.0% |
|||||
20 |
Laying of uPVC and DI pipes, Specials, DI valves and accessories for Raigampura Green Industrial and Techno Development Zone (Stage II) |
M/s. Brians Engineers (Pvt) ltd |
18.89 |
Apr-21 |
92.0% |
||||||||||||
GRANT/FUNDED BY OTHER INSTITUTIONS/PROJECT FUND |
|||||||||||||||||
21 |
Kesbewa- Pokunuwita Road pipe laying (Kahatuduwa Interchange to Pokunuwita Junction) |
RDA/SRCP/JCB/ADB/CP-02 |
M/s. MAGA Engineering |
RDA Awarded Contract |
Completed in 2020 |
0.00 |
100.0% |
100.0% |
Only the Supervision is done by NWSDB |
||||||||
22 |
Gonapola - Pokunuwita Road pipe laying |
M/s. MAGA Engineering |
RDA Awarded Contract |
Dec-21 |
25.0% |
||||||||||||
23 |
Rehabilitation & Improvements to Cross Junction to Digarolla Bridge |
RDA |
M/s. Solanma Engineering (Pvt) Ltd |
RDA Awarded Contract |
Completed in 2020 |
0.00 |
100.0% |
100.0% |
Only the Supervision is done by NWSDB |
||||||||
24 |
Construction of Pipeline Installation and Leak DetectionTraining Yard |
JICA |
USD 43,580.20 plus Rs.33,57 Mn |
Completed in 2020 |
100.0% |
||||||||||||
25 |
Construction of OIC Office for Horana OIC |
AMAIWSP |
AMAIWS Project Funded |
Mar-21 |
25% |
||||||||||||
26 |
Tender for Construction of 500m3 Capacity Ground Reservoir and Pump House for Dahampahangama Water Supply Scheme |
M/s Kandy Construction |
AMAIWS Project Funded (32.95 Mn) |
May-21 |
60% |
||||||||||||
27 |
Renovation of Regional Manager Office, Kalutara |
Southern Construction |
AMAIWS Project Funded (7.60 Mn) |
May-21 |
25% |
||||||||||||