Projects in Progress
Project Name | District | Type of Project | No. of Beneficiaries | Duration | Total Estimated Cost (Rs. million) | Actual Expenditure as at end 2010 (Rs. million) | Physical Progress % | |
From | To | |||||||
Central Province | ||||||||
Matale WS | Matale | Augmentation | 15,000 | Jan 1999 | Apr 2014 | 384.9 | 347.85 | 90 |
Kundasale Integrated WS - Stage II | Kandy | Augmentation | 130,000 | Jan 1998 | Dec 2014 | 1,400.00 | 1,276.73 | 85 |
Marassana WS | Kandy | New | 25,000 | Jan 1996 | Dec 2014 | 222 | 282.12 | 95 |
Thalawakele/ Lindula WS | Nuwara Eliya | Augmentation | 15,000 | Jan 2000 | Dec 2014 | 172 | 188.69 | 90 |
Palapathwela WS | Matale | Extension | 22,000 | Jan 2000 | Dec 2014 | 150 | 159.15 | 80 |
North Central Province | ||||||||
Hingurakkoda WS | Polonnaruwa | Augmentation | 6,000 | Jan 1996 | Dec 2015 | 130 | 124.94 | 98 |
Minneriya WS - Stage II | Polonnaruwa | Augmentation | 69,000 | Jan 2007 | Dec 2015 | 100 | 102.58 | 97 |
Medirigiriya WS - Stage I | Polonnaruwa | New | 60,000 | Jan 2007 | Dec 2015 | 638 | 574.66 | 70 |
Mahanelubewa WS | Anuradhapura | New | Dec 2010 | Dec 2014 | 129.7 | 113.74 | 97 | |
Ippalogama Housing Scheme WS | Anuradhapura | Extension | 18,000 | Jan 2007 | Dec 2014 | 798 | 598.12 | 92 |
Parasangaswewa | Anuradhapura | New | 1,000 | Jan 2013 | Dec 2013 | 31.6 | - | |
Deyata Kirula | Jan 2011 | Dec 2012 | 830 | 528.67 | 85 | |||
Eastern Province | ||||||||
Kantale WS | Trincomalee | Augmentation | 25,000 | Jan 1999 | Dec 2012 | 274.8 | 216.37 | 69 |
Tampalakamam WS | Trincomalee | Augmentation | 30,000 | Jan 1999 | Dec 2011 | 95.2 | 85 | 100 |
Transmission Main from Kantale to Tampalakamam | Trincomalee | Jan 2012 | Jan 2014 | 1,397.80 | 450 | 80 | ||
Wadinagala/ Wan - Ela WS | Jan 2012 | Dec 2015 | 808.5 | 19.04 | 10 | |||
Serunuwara WS | Trincomalee | Augmentation | 9,500 | Jan 2001 | Dec 2013 | 110.1 | 106.28 | 48 |
Dehiattakandiya WS - Stage I & II | Ampara | Augmentation | 16,000 | Jan 2007 | Dec 2012 | 300 | 250.74 | 99 |
Deyata Kirula 2013 | Ampara, Trincomalee | Jan 2012 | Dec 2013 | 1,875.00 | 26.89 | |||
Northern Province | ||||||||
Wastewater Treatment Plant for Kilinochchi Hospital | Jan 2012 | Dec 2012 | 36 | 6.95 | ||||
Mahawa/ Wariyapola/ Nikaweratiya WS | Jan 2012 | Dec 2014 | 505 | 40.7 | 90 | |||
North Western Province | ||||||||
Ibbagamuwa WS | 2012 | Dec 2014 | 239 | 62.02 | 4 | |||
Divulagane WS | Kurunegala | New | 1,950 | Jan 2013 | Oct 2015 | 46.7 | - | |
Dambadeniya | Jan 2012 | Dec 2016 | 796 | 3.26 | 2 | |||
Mahawa/ Wariyapola/ Nikaweratiya WS | Kurunegala | Augmentation | 45,000 | Jan 2000 | Dec 2014 | 996.7 | 856.31 | 89 |
Sabaragamuwa Province | ||||||||
Embilipitiya WS | Ratnapura | Augmentation | 84,000 | Sep 2003 | Dec 2013 | 363 | 387.88 | 94 |
Pelmadulla WS | Ratnapura | Augmentation | 14,500 | Jan 2000 | Dec 2015 | 384.2 | 355.47 | 96 |
Nivithigala WS | Ratnapura | Augmentation | 14,500 | Jan 1999 | Dec 2013 | 99.1 | 70.01 | 58 |
Udawalawa WS Stage I & II | Ratnapura | Augmentation | 9,400 | Jan 1999 | Dec 2014 | 973.6 | 654.59 | 90 |
Yatiyantota WS | Kegalle | Augmentation | 9,400 | Sep 2003 | Dec 2012 | 165.8 | 176.6 | 85 |
Godakawela WS | Ratnapura | Augmentation | 22,500 | Jan 1999 | Dec 2011 | 288.8 | 211.63 | 98 |
Pattampitiya WS | Kegalle | Extension | 7,300 | Jan 2001 | Dec 2011 | 145.2 | 143.61 | 100 |
Galigamuwa WS | Kegalle | New | 30,800 | Jan 2011 | Dec 2014 | 841 | 219.11 | 36 |
Madola WS | Kegalle | New | 4,500 | Jan 2013 | Dec 2013 | 132 | - | |
Kiriella WS | Ratnapura | 7,300 | Jan 2011 | Dec 2014 | 205 | 21.92 | 97 | |
Southern Province | ||||||||
Akuressa WS | Matara | New | 15,000 | Jan 1999 | Dec 2011 | 338.6 | 272.66 | 100 |
Thihagoda WS | Matara | New | 7,500 | Jan 2001 | Dec 2011 | 162.1 | 172.46 | 100 |
Baddegama WS | Galle | New | 33,830 | Jul 2013 | Aug 2015 | 441 | ||
Gonapinuwala WS | Galle | New | 20,825 | Jul 2013 | Aug 2015 | 350 | ||
Dikkumbura WS | Galle | New | 17,130 | Jul 2013 | Aug 2015 | 275 | ||
Bentota WS | Galle | New | 18,850 | Jul 2013 | Aug 2015 | 700 | ||
Udugama WS | Galle | New | 6,000 | Apr 2001 | Dec 2011 | 145.5 | 139.51 | 100 |
Pitabeddara WS | Matara | New | 6,000 | Jan 2001 | Dec 2011 | 130.3 | 102.5 | 98 |
Bonavista Kanda Area WS | Matara | 600 | Jan 2010 | Dec 2012 | 57 | 44.03 | 99 | |
Hakmana WS | Matara | 10,000 | Jan 2008 | Dec 2013 | 383.4 | 123.76 | 60 | |
Uva Province | ||||||||
Ohiya Transmission | Badulla | New | 10,000 | Feb 1999 | Dec 2013 | 264.7 | 206.23 | 96 |
Monaragala WS - Stage II | Monaragala | New | 10,000 | Jun 1999 | Dec 2013 | 154.8 | 142.17 | 98 |
Badalkumbura WS | Monaragala | New | 22,000 | Oct 1999 | Dec 2013 | 124.4 | 97.18 | 86 |
Buttala WS | Monaragala | 2,600 | Jan 2010 | Dec 2012 | 295 | 287.44 | 100 | |
Ambagasduwa WS | Badulla | New | 6,000 | Jun 1999 | Dec 2013 | 382 | 137.22 | 72 |
Wellawaya WS | Monaragala | Augmentation | 6,000 | Jan 2007 | Dec 2014 | 250 | 96.81 | 65 |
Western Province | ||||||||
Rehabilitation of Western Central WS | Colombo | Rehabilitation | 162,500 | 2009 | Dec 2012 | 1,300.00 | 1,317.51 | 97 |
Kirindiwela WS | Gampaha | New | 8,000 | May 1998 | Dec 2013 | 198 | 172.63 | 90 |
Nittambuwa/ Veyangoda WS | Gampaha | Augmentation | 15,000 | Oct 1999 | Dec 2013 | 210.7 | 201.96 | 96 |
Kalutara Integrated WS - Stage II | Kalutara | Augmentation | 210,000 | Jan 2008 | Dec 2014 | 1,366.20 | 789.16 | 58 |
Jalthara - Ranala WS | Colombo | 17,920 | Jan 2010 | Dec 2013 | 217.2 | 86.15 | 27 | |
Katunayake WS - Stage WS 1 & II | Gampaha | Augmentation | 29,000 | Jan 2005 | Dec 2014 | 470 | 265.03 | 62 |
Kolonnawa Sewerage | Colombo | New | 20,000 | 1,296.00 | - | |||
Inter Provincial Projects/ Programmes | ||||||||
Small Schemes & Disaster Management Programme and Urgent Improvements (TCE Less than Rs.10 M ) a. Madola b. PahalaKaduganna c. Eheliyagoda d. Extension to Batuwatta & Kopparamessa e. Menikdola f. Kabagamuwa g. Makurakanda h. Ellawala |
10,000 | Jan 2010 | Dec 2012 | 92.5 | 88.9 | |||
Investigations, Surveys & Feasibility Studies for new project proposals | 100 | 12.55 | ||||||
Utility shiffting / replacement owing to accelerated Pradeshiya Sabha Road Development Programmmes | 300 | 25.05 |
* Abbreviations | ||
WS | : | Water Supply |
Emerging small townships Water Supply Projects Click here.....
Name | |
ADB V(a) | Click here..... |
(b) | Click here.... |
(c) | Click here..... |
Ampara JICA | Click here..... |
Ampara Phase III | Click here..... |
Anuradhapura | Click here..... |
Badulla | Click here..... |
CWSSP | Click here..... |
Dambulla | Click here..... |
GColombo | Click here..... |
Jaffna | Click here..... |
Kalatuwawa | Click here |
Kalu Ganga | Click here..... |
Kilinochchi | Click here..... |
Kolonna | Click here..... |
Mahiyangana | Click here..... |
Monaragala | Click here..... |
Project Name (Donor) | District | Type of Project | No. of Beneficiaries | Duration | Total Estimated Cost (Rs. million) | Actual Expenditure as at end 2010 (Rs. million) | Physical Progress % | |
From | To | |||||||
Central Province | ||||||||
Water Sector Development Project 1 Sub Project 4 Greater Kandy WS Phase I Stage II (JICA) | Kandy | Augmentation | 616,000 | Oct 2007 | Jul 2012 | 4,164.00 | 4,681.63 | 94 |
Greater Dambulla WS - Stage 1 (INDIA) | Nuwara Eliya | Augmentation | 2012 | Jul 2014 | 9,593.00 | 5,808.50 | 23 | |
Eastern Province | ||||||||
Eastern Coastal Towns of Ampara District (ECTAD) WS Phase II (Australia) | Ampara | New | 161,400 | Oct 2002 | Dec 2010 | 11,078.20 | 10,712.13 | 100 |
Eastern Province Water Supply Development Project (JICA) | Ampara | New | 2010 | 2015 | 6,526.00 | 1,407.16 | 70 | |
Integrated Water Supply Scheme for the Unserved Area of Ampara District Phase III (Australia) | Ampara | New | 80,000 | 2007 | 2015 | 18,012.00 | 9,904.30 | 36 |
Northern Province | ||||||||
Jaffna Killinochchi Water Supply & Sanitation (ADB VI) | Jaffna | Augmentation | 15,000 | 2011 | 2016 | 18,328.20 | 194.56 | 15 |
Killinochchi Rehabilitation Water Supply Project (JICA) | 15,000 | 2013 | 2015 | 1,900.00 | - | |||
Immediate Arragements to provide Water Supply to Kilinochchi (New 2 KR) (JICA ) | 2013 | 2015 | 260 | 150 | 65 | |||
North Central Province | ||||||||
Thambuttegama WS (China) | Kurunegala | New | 2014 | 2017 | 1,805.00 | - | ||
Anuradhapura North Intergrated Water Supply (JICA) | 2013 | 2015 | 9,736.00 | - | ||||
Southern Province | ||||||||
Ruhunupura WS Development (Korea) | Jan 2011 | Mar 2013 | 13,131.30 | 5,378.20 | 46 | |||
Kirama, Katuwana, Middeniya & Angunakolapelessa Integrated WS (China) | Galle | Augmentation | 160,000 | Jan 2012 | Jan 2013 | 2,662.00 | - | |
Rehabilitation & Augmentation of Kirindioya Water Supply (Austria) | Hambantota | Augmentation | 30,000 | Feb 2007 | Dec 2009 | 2,104.83 | 1,914.25 | 100 |
Uva Province | ||||||||
Badulla - Haliela and Ella Integated WS (US Exim Bank) | 2013 | 2015 | 10,396.50 | 5.1 | ||||
Mahiyangana Water Supply (Austria) | 2013 | 2016 | 1,785.00 | - | ||||
Western Province | ||||||||
Water Sector Development Project I Towns North of Colombo WS -stage II (JICA) |
Colombo | Extension | 200,000 | 2007 | 2014 | 6,490.00 | 5,750.36 | 97 |
Kelani Right Bank WTP (DANIDA) | Colombo | New | 1,500,000 | Oct 2008 | Dec 2013 | 12,000.00 | 9,477.31 | 98 |
Rehabilitation & Augmentation of Labugama - Kalatuwawa WTP (Hangary) | Colombo | Rehabilitation | 375,000 | 2013 | 2016 | 8,100.00 | 1.29 | - |
Augmentation of Negombo WS (DUTCH) | Gampaha | Augmentation | 137,500 | 2008 | 2013 | 7,302.00 | 6,703.69 | 98 |
Water Sector Development Project I Greater Colombo Water Rehabilitation (JICA) |
Colombo | Rehabilitation | 100,000 | 2007 | 2015 | 4,785.00 | 3,476.78 | 74 |
Water Sector Development Project II (JICA) Kaluganga Water Supply Project Phase I -Stage II & Non Revenue Water Reduction in Colombo City (NRW Master Plan) |
Jul 2008 | Dec 2015 | 10,846.00 | 4,650.60 | 66 | |||
Consultancy Services for Non Revenue Water (NRW) Engineering Study, Master Plan Update and Institutional Development | Oct 2011 | Jun 2013 | 412.1 | - | ||||
Energy Conservation Project at Ambatale WTP (GERMAN) | 2012 | 2014 | 6,220.00 | - | ||||
Capacity Development Project for NRW reduction in Colombo City (JICA) | 2010 | 2011 | 201 | 30.6 | 100 | |||
Colombo Water Supply Service Improvement Project (ADB) | 2012 | 2018 | 28,800.00 | 8.12 | ||||
Katana WS (China) | 2014 | 2015 | 1,641.00 | - | ||||
Water Treatment Facilities Moratuwa / Panadura, Ambatale and in Negombo (Spanish) [formerly Galagoda WSS] | Colombo, Gampaha | New | 10,000 | Oct 2007 | Dec 2009 | 2,690.00 | 2,672.34 | 100 |
Sabaragamuwa Province | ||||||||
Greater Ratnapura Water Supply Project (Spain) | Jan 2012 | Dec 2016 | 9,928.00 | - | ||||
Kolonna/ Balangoda Water Supply Project (Belgium) | 2011 | 2015 | 4,658.00 | 1,244.50 | 5 | |||
North Western Province | ||||||||
Greater Kurunegala (China) | Jan 2013 | Dec 2015 | 11,943.00 | - | ||||
Wandura Pinu Ella WS (China) | Jan 2012 | 9,756.00 | - | |||||
Inter Provincial Projects/ Programmes | ||||||||
Secondary Towns Rural Community Based WS & Sanitation (ADB 4th project) | Polonnaruwa, Anuradhapura, Trincomalee, Hambantota, Batticaloa | New | 968,000 (Water) & 171,500 (Sanitation) | Jan 2004 | 2013 | 29,680.00 | 25,692.94 | 95 |
Dry zone urban Water & Sanitation Project(ADB V) | 86,000 | Jun 2009 | Jun 2014 | 13,029.60 | 1,494.19 | 31 | ||
Hambantota/ Ambalantota/ Weligama/ Kataragama Implementation Project & Badulla, Bandarawela Integrated Feasibility Studies (UNIHA) | Hambantota, Matara | Augmentation | 150000 & SLI 200,000 | Nov 2004 | Dec 2013 | 2,126.00 | 1,767.88 | 98 |
* Abbreviations | ||
ADB | : | Asian Development Bank |
DANIDA | : | DANish International Development Agency |
JICA | : | Japan International Cooperation Agency |
KfW | : | Credit for Reconstruction |
SLI | : | Service Level Improvements |
UNICEF | : | United Nations International Children's Fund |
WS | : | Water Supply |
Project Name | District | No. of Beneficiaries | Duration | Total Estimated Cost (Rs. million) | Actual Expenditure as at end 2010 (Rs. million) | |
From | To | |||||
Water Sanitation & Hygine Programme (WASH program) | Mulaitivu, Ampara, Hambantota, Kalutara, Tangalle & Thirukkovil | 2011 | 2013 | 240 | 141.57 | |
Tsunami Affected Areas Rebuilding Fund Project - Component D (ADB) | Trincomalee, Batticaloa & Hambantota | 14253 families | 2,005 | 2011 | 1,230.00 | 919.78 |
Assistance for Emergency Measures and Ambalangoda WSS (KfW) | Galle | 2,007 | 2011 | 4,201.70 | 4,898.52 | |
Trincomalee Integrated Infrastructure Project (French Development /Agency - AFD-Component 2) | Trincomalee | 2006 | 2013 | 2,819.30 | 1,983.18 | |
IFRC Funded Tsunami Transmission System Improvement (IFRC) | Jaffna, Ampara, Hambantota, Matara & Galle | 2005 | 2011 | 3,785.00 | 2,422.16 | |
Greater Trincomalee Integrated Water Supply (RPE France) | Trincomalee | 2,006 | 2013 | 2,881.00 | 2,011.17 |
* Abbreviations | ||
ADB | : | Asian Development Bank |
IFRC | : | International Federation of Red Cross |
KfW | : | Reconstruction Credit Institute |
UNICEF | : | United Nations International Children's Fund |
USAID | : | United States Agency for International Development |
Project Name | District | Type of Project | No. of Beneficiaries | Duration | Total Estimated Cost (Rs. million) | Actual Expenditure as at end 2010 (Rs. million) | Physical Progress % | |
From | To | |||||||
Central Province | ||||||||
Water Sector Development Project 1 Sub Project 1 Sewage disposal system for Kandy Municipal area (JICA) |
Kandy | New | 49,700 | Oct 2007 | Dec 2017 | 22,585.00 | 797.99 | 3 |
Southern Province | ||||||||
Galle Sewerage (China) | Galle | 2010 | 2014 | 3,200.00 | - | |||
Kataragama Sacred City Waste Water Disposal | Monaragala | Augmentation | 15,000 | 615.0 | ||||
Western Province | ||||||||
Rehabilitation & Upgrading of Southern Catchments of GC Sewerage (Austrian) | Colombo | Rehabilitation | 300,000 | 2007 | 2010 | 2,222.00 | 1,881.87 | 100 |
Waste Water Disposal System for Ratmalana/ Moratuwa & Ja-Ela/ Ekala Areas (SIDA) | Colombo | New | 94,500 | 2008 | 2013 | 16,155.00 | 12,695.26 | 85 |
Greater Colombo Waste Water Managemet (ADB) | Colombo | Rehabilitation | 500,000 | 2010 | 2014 | 1,012.00 | 36.98 | 2 |
GPOBA funded project for increasing Household Access to Sewerage Services (World Bank) | 2012 | 2014 | 1,095.00 | 3.06 | ||||
Maharagama Boralesgamuwa (China) | 2013 | 2015 | 2,200.00 | - | ||||
Hospital Sewerage System Improvement (China) | 2012 | 2,100.00 | - | |||||
North Western Province | ||||||||
Greater Kurunegala Water Supply & Sanitation | Kurunegala | Augmentation/ New | 64,000 | 8,283.0 |
* Abbreviations | ||
ADB | : | Asian Development Bank |
DANIDA | : | DANish International Development Agency |
JICA | : | Japan International Cooperation Agency |
SIDA | : | Swedish International Development Cooperation Agency |
WS | : | Water Supply |
Global partnership on Output Based - Aid project is implementing under the funds from World Bank, GOSL, NWSDB. Main objectives of the project are to increase house hold Access to domestic sanitation in Greater Colombo for low income households.
It is targeted to give 8800 hoseholds sanitation facilityes and it will be benefited for 44000 people in Dehiwala/Mt. Lavinia, Kolonnawa, Moratuwa and Jaela/Ekala area.
Details of GPOBA Project and SPEARs | |
Spear Badovita | Download |
Spear DC | Download |
Spear Diyawarapura | Download |
Spear Lunawa | Download |
Spear On-Site | Download |
Spear SCE Stage | Download |
Spear Tsunami | Download |
Resettlement Plan Click here.....
Environmental Impact Assessment Report click here.......
THE GOVERNMENT OF THE DEMOCRATIC SOCIALIST REPUBLIC OF SRI LANKA
MINISTRY OF CITY PLANNING AND WATER SUPPLY
NATIONAL WATER SUPPLY AND DRAINAGE BOARD
Date : 08/02/2017
Loan No. & Title : ADB Loan No. 3030-SRI;
AFD Loan No.:- CLK 1008 – 01P AFD Credit Facilities
Greater Colombo Water and Wastewater Management Improvement Investment Programme - Project 2;
AFD Contractual Co Financing - Ambathale Water Supply System Improvement & Energy Saving Project
Contract No. : GCWWMIIP/AFD/EQUIP/OPER/ICB/06
Title :Bidding Document for Machinery and Equipment for Operation and Maintenance Activities of Western Production Section
Deadline for Submission of Bids: 29/03/2017, 10:00 hours (Local time)
Please refer the attached IFB for more details.Click here.....
Write comment (0 Comments)
Ongoing Projects and New Projects under Corporate Plan 2020-2025
No |
Project |
WTP Capacity (m3/d) |
New Connections (Domestic) Nos. |
Expected Date of Completion |
||
Foreign Financing |
||||||
1 |
Polgahawela, Pothuhera and Alawwa Integrated Water Supply project |
29,000 |
32,500 |
Apr-21 |
||
2 |
Kelani Right Bank WSP |
180,000 |
17,500 |
Oct-20 |
||
3 |
Greater Matale WSP |
75,000 |
20,000 |
Dec-20 |
||
4 |
Gampaha, Attanagalla & Minuwangoda Integrated Water Supply Scheme |
54,000 |
18,975 |
Dec-22 |
||
5 |
Aluthgama, Mathugama and Agalawatta Integrated Water Supply Project |
74,250 |
29,000 |
Apr-21 |
||
6 |
Matara Stage IV WSP |
30,000 |
9,000 |
Mar-22 |
||
7 |
Thambuttegama WSP |
18,000 |
25,000 |
Dec-22 |
||
8 |
Katana WSP |
22,000 |
Nov-20 |
|||
9 |
Replacing of Transmission and Distribution Mains from Orugodawatta to Kaduwela Project |
- |
- |
Dec-21 |
||
10 |
Hemmathagama Water Supply Project |
21,000 |
14,400 |
Jun-22 |
||
11 |
Deduru Oya Water Supply Project |
15,000 |
14,750 |
Nov-20 |
||
12 |
Anamaduwa Integrated Water Supply Project |
11,000 |
6,450 |
Nov-21 |
||
13 |
Kandy North Pathadumbara Integrated Water Supply Project |
50,000 |
41,000 |
Nov-22 |
||
14 |
Kirama Katuwana Integrated Water Supply Project |
3,500 |
3,850 |
Aug-21 |
||
15 |
Dry Zone Urban Water & Sanitation Project |
Jul-20 |
||||
16 |
Jaffna Kilinochchi Water Supply & |
24,000 |
60,000 |
Sep-23 |
||
17 |
Colombo Water Supply service Improvement Project 1 (Package 1) |
Dec-20 |
||||
18 |
Colombo Water Supply service Improvement Project 1 (Package 2) |
Sep-21 |
||||
19 |
Colombo Water Supply service Improvement Project 2 (Package 3 and Package 4) |
Dec-22 |
||||
20 |
Ambatale Water Supply System Improvement & Energy Saving Project |
Dec-22 |
||||
21 |
Anuradhapura North Water Supply Project - Phase 1 |
9,400 |
9,428 |
Mar-21 |
||
22 |
Anuradhapura North Water Supply Project Phase II |
17,500 |
25,000 |
Dec-24 |
||
23 |
Kalu Ganga Water Supply Expansion Project (1) |
140,000 |
185,000 |
Dec-25 |
||
24 |
Ruwanwella Water Supply project |
4,000 |
4,800 |
Jun-22 |
||
Local Financing Projects |
||||||
25 |
Towns East of Colombo (Package 1) WSP |
Feb-20 |
||||
26 |
Towns East of Colombo (Package 2) WSP |
Dec-20 |
||||
27 |
Towns East of Colombo (Package 3) WSP |
32,000 |
Aug-20 |
|||
28 |
Wilgamuwa WSP |
5,500 |
6,375 |
Dec-20 |
||
29 |
Laggala WSP |
4,000 |
5,125 |
Mar-21 |
||
30 |
Galageddara Mawathagama WSP |
7,140 |
Aug-20 |
|||
31 |
Medirigiriya WSP |
4,500 |
Jul-20 |
|||
32 |
Galle Cluster WSP |
12,505 |
Nov-20 |
|||
33 |
Attampitiya WSP |
3,000 |
700 |
Feb-21 |
||
34 |
Greater Rathnapura WSP |
5,950 |
Dec-20 |
|||
35 |
Giridara WSP |
4,500 |
Dec-20 |
|||
36 |
Second Phase of the Pipe Laying Project from Andaragasyaya underground tank to Gannoruwa in Hambantota District |
2,800 |
Dec-20 |
|||
37 |
Thissamaharmaya WSS |
2,000 |
Dec-20 |
|||
38 |
Water Supply Facilities for Resettlement Villages in Kegalle District |
800 |
Jul-21 |
|||
39 |
Augmentation of Trincomalee Water Supply Scheme |
Dec-21 |
||||
40 |
Madhu Church Water Supply Scheme |
2,900 |
Dec-21 |
|||
41 |
Project for Enhancement of Operational Efficiency and Assets Management Capacity of RSC (Western South) NWS&DB) |
Jun-21 |
||||
42 |
Matara Short Term Improvements |
5,000 |
Dec-21 |
|||
43 |
Bandarawela WSS improvement project |
2,500 |
Aug-20 |
|||
44 |
Dankotuwa WSS |
4,590 |
May-21 |
|||
Project Name |
Water Source |
Production Increase (m3/day) |
Approval |
Length of Pipe Laying (km) |
|
Western Central RSC |
553,000 |
53,000 |
4,250 |
||
Colombo District |
553,000 |
53,000 |
4,250 |
||
1 |
Ambatale Water Treatment Plant Expansion Project |
550,000 |
50,000 |
||
2 |
Improvement of Awissawella Water Treatment Plant |
3,000 |
3,000 |
4,250 |
|
Western North RSC |
32,750 |
15,750 |
19,275 |
12 |
|
Gampaha District |
32,750 |
15,750 |
19,275 |
12 |
|
3 |
Augmentation of Gampaha WTP |
3,500 |
2,000 |
2,500 |
|
4 |
Augmentation of Divulapitiya WTP |
1,250 |
1,750 |
1,875 |
|
5 |
Rehabilitation of Raddolugama WSS |
7,000 |
2,000 |
2,500 |
|
6 |
Extension of Intake Structure at Pugoda |
6,000 |
|||
7 |
Augmentation of Ranpokunawatta WTP |
6,000 |
4,000 |
4,900 |
12 |
8 |
Augmentation of Veyangoda WSS |
3,000 |
2,000 |
2,500 |
|
9 |
Augmentation of Yakkala WSS |
3,000 |
2,000 |
2,500 |
|
10 |
Augmentation of Nittambuwa WSS |
3,000 |
2,000 |
2,500 |
|
Western South RSC |
120,550 |
11,000 |
11,000 |
1 |
|
Kalutara District |
120,550 |
11,000 |
11,000 |
1 |
|
11 |
Ingiriya Water Supply Improvement Project |
550 |
1,000 |
1,000 |
|
12 |
Capacity Improvement of Kadana WTP |
120,000 |
10,000 |
10,000 |
|
North Western RSC |
6,100 |
1,800 |
3,886 |
20 |
|
Kurunegala District |
500 |
500 |
500 |
3 |
|
13 |
Mawathagama Water Supply Project |
500 |
500 |
500 |
3 |
Puttalam District |
5,600 |
1,300 |
3,386 |
17 |
|
14 |
Nattandiya - Wennappuwa Water Supply Scheme |
1,100 |
400 |
1,886 |
9 |
15 |
Kakkapalliya Water Supply Project |
4,500 |
900 |
1,500 |
8 |
North Central RSC |
66,500 |
50,500 |
39,305 |
324 |
|
Anuradhapura District |
38,000 |
18,500 |
21,645 |
88 |
|
16 |
Augmentation of Thissawewa WTP |
4,500 |
4,500 |
4,668 |
50 |
17 |
Augmentation of Thuruwila WTP |
18,000 |
4,500 |
5,628 |
|
18 |
Construction of a 5,000m3/day capacity WTP at Galnewa |
2,000 |
5,000 |
4,840 |
1 |
19 |
Kalawewa WSS Improvements |
13,500 |
4,500 |
6,509 |
37 |
Polonnaruwa District |
28,500 |
32,000 |
17,660 |
237 |
|
20 |
Improvements to Minneriya WTP & WSS |
9,000 |
4,500 |
3,588 |
1 |
21 |
Augmentation of Polonnaruwa Old WTP |
6,000 |
500 |
0 |
11 |
22 |
Augmentation of Gallella WTP |
13,500 |
18,000 |
1,572 |
|
23 |
Medirigiriya WTP -Phase 2 |
- |
9,000 |
12,500 |
225 |
North RSC |
24,855 |
19,817 |
31,540 |
235 |
|
Jaffna District |
10,270 |
3,120 |
6,725 |
76 |
|
24 |
Augmentation of Delft WSS |
100 |
100 |
350 |
18 |
25 |
Service Level Improvement in Naranthanai WSS |
- |
100 |
825 |
10 |
26 |
Improvement to Existing Water Supply Schemes in Thaiyaddi & Vadakkachchi |
170 |
740 |
1,250 |
45 |
27 |
Improvement of WTP in Thottaveli, Murunkan & Point Pedro |
2,180 |
4,300 |
3 |
|
Kilinochchi District |
7,600 |
9,815 |
58 |
||
28 |
Improvement to Existing WTP at Kilinochchi |
3,800 |
4,000 |
||
29 |
Improvement to Akkarayan WSS |
800 |
|||
30 |
Paranthan to Palai Transmission Main |
2,200 |
25 |
||
31 |
Groundwater Source Development in Northern region |
3,800 |
2,815 |
33 |
|
Mannar District |
1,147 |
4,400 |
84 |
||
32 |
Rehabilitation of Thalai Mannar WSS |
900 |
1,800 |
49 |
|
33 |
Service level Improvement in Musali Water supply scheme |
247 |
2,600 |
35 |
|
Mullaitivu District |
1,200 |
3,700 |
18 |
||
34 |
Service Level Improvement in Mankulam Water supply scheme |
700 |
|||
35 |
Augmentation of Oddusuddan & Nedunkerney WSS (stage 1 & 2) |
600 |
1,500 |
||
36 |
Augmentation of Pandiankulam & Mallavi WSS |
600 |
1,500 |
18 |
|
Vavuniya District |
6,750 |
6,900 |
|||
37 |
Peraru Bund raising for additional 0.8MCM |
6,000 |
4,400 |
||
38 |
Service Level Improvement in Cheddikulam WSP |
750 |
1,500 |
||
39 |
Improvement to Omanthai WSS |
1,000 |
|||
Central RSC |
11,500 |
7,000 |
21 |
||
Kandy District |
11,500 |
7,000 |
21 |
||
40 |
Installation of 1500m3/day package TP for Medadumbara WSS & Pipe Laying |
Kota Ganga |
1,500 |
18 |
|
41 |
Augmentation of Balagolla WTP |
6,000 |
3,500 |
||
42 |
Augmentation of Marassana WTP |
4,000 |
3,500 |
3 |
|
Southern RSC |
67,900 |
47,600 |
228 |
||
Galle District |
9,000 |
6,300 |
57 |
||
43 |
Capacity improvement and distribution expansion project of Baddegama WSS |
6,000 |
3,000 |
30 |
|
44 |
Capacity improvement and distribution expansion project of Pitigala WSS |
1,000 |
1,000 |
3 |
|
45 |
Capacity improvement and distribution expansion project of Udugama WSS |
2,000 |
2,300 |
25 |
|
Hambanthota District |
53,000 |
35,500 |
169 |
||
46 |
Capacity improvement and distribution expansion project of Lunugamwehera WSS Phase I & II |
6,000 |
3,000 |
12 |
|
47 |
Capacity improvement and distribution expansion project of Kataragama WSS (Short Term) |
9,000 |
6,500 |
34 |
|
48 |
Barawakumbuka short term Phase I |
6,000 |
5 |
||
49 |
Barawakumbuka short term Phase II |
5,000 |
49 |
||
50 |
Nawayalawila source Improvement Project of Tangalle WSS |
6,000 |
4,000 |
||
51 |
Augmentation of Muruthawela WSS and Distribution Expansion |
6,000 |
5,000 |
23 |
|
52 |
Augmentation of Kattakaduwa WTP and distribution expansion project of Ranna WSS |
12,000 |
12,000 |
6,000 |
|
53 |
Construction of 6,000 m3/day capacity WTP and Transmission and Distribution expansion for Wakamulla WSS (Phase 1) |
1,200 |
6,000 |
5,000 |
1 |
54 |
Wakamulla WSS (Phase 2) |
0 |
43 |
||
55 |
Augmentation of Bundala WSS |
300 |
1,000 |
500 |
2 |
56 |
Augmentation of Katuwana WSS |
800 |
1,000 |
500 |
|
Matara District |
9,085 |
5,900 |
5,800 |
3 |
|
57 |
Augmentation of Hallala WSS |
8,000 |
3,000 |
3,000 |
|
58 |
Capacity Enhancement & Distribution Expansion project of Hakmana WSS |
900 |
900 |
300 |
3 |
59 |
Capacity improvement and distribution expansion project of Urubokka WSP |
185 |
2,000 |
2,500 |
|
Sabaragamuwa RSC |
52,400 |
32,100 |
23,220 |
159 |
|
Kegalle District |
39,900 |
22,100 |
12,820 |
41 |
|
60 |
Integration of Kegalle WSS |
8,500 |
2,500 |
1,500 |
|
61 |
Upgrading Moronthota WTP and associated Transmission and Distribution System improvements |
11,250 |
6,750 |
- |
3 |
62 |
Upgrading Mawanella WTP and associated Transmission and Distribution System improvements |
15,000 |
3,000 |
3,000 |
12 |
63 |
Supply and laying of gravity transmission main to Adurapotha tank |
- |
- |
5 |
|
64 |
Improvements of the Intake weir of Yatiyanthota Water Treatment Plant |
950 |
1,050 |
1,320 |
|
65 |
Upgrading Dehiowita WTP & Distribution Improvements |
1,000 |
2,000 |
2,500 |
12 |
66 |
Upgrading existing Ruwanwella water treatment plant |
2,000 |
4,000 |
2,000 |
|
67 |
Upgrading existing Warakapola WTP & Distribution Improvements |
1,200 |
2,800 |
2,500 |
9 |
Rathnapura District |
12,500 |
10,000 |
10,400 |
118 |
|
68 |
Upgrading Pelmadulla WTP & Distribution Improvements |
3,000 |
1,500 |
3,000 |
29 |
69 |
Augmentation of old Balangoda WTP & Laying of DI pumping main |
3,000 |
4,000 |
2,000 |
1 |
70 |
Construction of Intake at Thalavitiya, Raw water transmission and Aerator for improving quality of service in Eheliyagoda WSS |
1,400 |
- |
- |
8 |
71 |
Improving of existing Kiriella WTP & Distribution Improvements |
600 |
- |
600 |
8 |
72 |
Augmentation of Kahawatte WTP and distribution expansion to Opanayake |
4,500 |
4,500 |
4,800 |
73 |
Uva RSC |
23,058 |
26,550 |
28,802 |
136 |
|
Badulla District |
3,308 |
6,850 |
10,603 |
96 |
|
73 |
Improvements to Nayabedda water source and distribution improvement in Bandarawela and suburb area |
1,000 |
4,055 |
42 |
|
74 |
Water Treatment Improvement in Badulla District WSS |
3,268 |
1,350 |
1,333 |
|
75 |
Improvemnts to Kandekatiya wss |
40 |
4,500 |
5,215 |
54 |
Monaragala District |
19,750 |
19,700 |
18,199 |
40 |
|
76 |
Improvement to Icepihilla WTP, Wellawaya WSS |
2,000 |
2,000 |
2,319 |
|
77 |
Wellawaya Stage II phase I |
9,250 |
10,000 |
6,955 |
20 |
78 |
Water Treatment Improvement in Monaragala District WSS(Medagama, Siyabalanduwa, Sewanagala) |
3,400 |
200 |
232 |
1 |
79 |
Capacity and Distribution improvement to Buttala WSS |
4,300 |
1,500 |
1,738 |
19 |
80 |
Bibila Medagama WSS -Phase l |
800 |
6,000 |
6,955 |
1 |
East RSC |
30,600 |
15,850 |
22,594 |
269 |
|
Ampara District |
20,900 |
1,750 |
7,050 |
86 |
|
81 |
Improvement of Service Level at Panama WSS |
450 |
1,250 |
1 |
|
82 |
Improvement to Thirukkovil WSS |
6,500 |
- |
4,725 |
14 |
83 |
Improvement of Dehiytakandiya & Lihiniyagama WSS |
4,700 |
600 |
550 |
54 |
84 |
Improvement of Bangalawadiya WTP at Sammanthurai |
9,000 |
- |
- |
|
85 |
Improvement of Padiyathalawa WSS |
700 |
700 |
525 |
17 |
Batticaloa District |
5,000 |
805 |
48 |
||
86 |
Increase service coverage in Unnichchai and surrounding areas |
805 |
28 |
||
87 |
Augmentation of Valachchanai Paper Mill WSS |
5,000 |
0 |
20 |
|
Trincomalee District |
9,700 |
9,100 |
14,739 |
136 |
|
88 |
Distribution improvement in Kinniya DS area |
2,025 |
4 |
||
89 |
Upgrading Muthur WTP & Intake improvement at Neelapola |
8,500 |
8,500 |
2,230 |
|
90 |
Service level improvement to Trincomalee City and Surrounding areas |
3,525 |
15 |
||
91 |
Increasing service coverage and Service level improvement in Dehiwatha , Thoppur and surrounding areas |
1,210 |
91 |
||
92 |
Water quality improvement in Pulmoddai WSS |
1,200 |
600 |
1,910 |
|
93 |
Water Source improvement in Eachchliampattu WSS |
804 |
8 |
||
94 |
Water supply extension to Naddouththu and Sorrounding areas from Muthu WTP |
3,035 |
17 |
||
95 |
Intake Improvement of Integrated Trincomalee WSS at Allai Kanthale |
1 |
|||
TOTAL |
295,767 |
238,472 |
1,405 |
Project Name |
Length of Pipe Laying(km) |
Total New Connections (Nos.) |
|
Distribution Infilling & Expansion |
4,656 |
243,454 |
|
Western Central RSC |
118 |
13,450 |
|
Colombo District |
118 |
13,450 |
|
1 |
Laying of Pipes Along Infilling Areas of Towns East of Colombo District Water Supply Project -Phase I |
28 |
4,000 |
2 |
Laying of Pipes Along Infilling Areas of Towns East of Colombo District Water Supply Project -Phase II |
90 |
9,450 |
Western North RSC |
635 |
33,500 |
|
Gampaha District |
635 |
33,500 |
|
3 |
Supply & laying of pipes from Delgoda to Belummahara |
10 |
2,000 |
4 |
Kelaniya Distribution Improvement - Phase I (Water Supply to Parakandeniya Area in Gampaha District |
18 |
1,500 |
5 |
Implementation of infilling work in ongoing Katana Water Supply Project Area - Stage I |
21 |
1,500 |
6 |
Kelaniya Distribution Improvement - Phase II |
10 |
1,500 |
7 |
Implementation of balance part of distribution network in ongoing Gampaha Attanagalla and Minuwangoda Integrated Water Supply Scheme - Gampaha and Nittambuwa area |
220 |
10,000 |
8 |
Implementation of infilling work in ongoing Katana Water Supply Project Area - Stage II |
21 |
1,500 |
9 |
Distribution Improvement in Gampaha - Stage I. |
20 |
1,500 |
10 |
Infilling work in Katana Water Supply Project Area - Stage III |
195 |
5,500 |
11 |
Infilling Work of Gampaha, Attanagalla and Minuwangoda Integrated Water Supply Scheme |
120 |
8,500 |
Western South RSC |
225 |
11,000 |
|
Kalutara District |
225 |
11,000 |
|
12 |
Distribution expansion of Matugama / Agalawatta areas in Kalutara district |
225 |
11,000 |
North Western RSC |
1,247 |
43,985 |
|
Kurunegala District |
747 |
22,070 |
|
13 |
Distribution Expansion in Deduru Oya Integrated Water Supply Project & Ambanpola, Galgamuwa Area |
205 |
9,200 |
14 |
Distribution Expansion in Polgahawela - Pothuhera - Alawwa Integrated Water Supply Project |
542 |
12,870 |
Puttalam District |
500 |
13,500 |
|
15 |
Distribution Expansion in Anamaduwa Integrated Water Supply Project |
500 |
13,500 |
North Central RSC |
199 |
8,466 |
|
Anuradhapura District |
189 |
8,396 |
|
16 |
Distribution infilling and extension of Habarana WSS |
47 |
1,554 |
17 |
Distribution infilling and extension of Madatugama WSS |
142 |
6,842 |
Polonnaruwa District |
9 |
70 |
|
18 |
Distribution infilling of Hingurakgoda WSS |
3 |
25 |
19 |
Distribution infilling of Minneriya WSS |
2 |
15 |
20 |
Distribution infilling of Polonnaruwa & Gallela WSS |
5 |
30 |
North RSC |
184 |
4,575 |
|
Jaffna District |
68 |
1,725 |
|
21 |
Infilling of Distribution lines in Jaffna Region (Jaffna, Kilinochchi, Mullaithivu) |
68 |
1,725 |
Mullaitivu District |
30 |
500 |
|
22 |
Infilling and Distribution Expansion of WaSSIP (Kilinochchi/Mullaithivu) in Kilinochchi & Mullaithivu |
30 |
500 |
Vavuniya District |
86 |
2,350 |
|
23 |
Infilling of Distribution lines in Vavuniya Region (Mannar WSS, Adampan WSS, Thevanpiddy WSS, Vidathalthevu WSS and vavuniya WSS-2 Stages ) |
86 |
2,350 |
Central RSC |
272 |
24,179 |
|
Kandy District |
191 |
22,200 |
|
24 |
Distribution & Transmission of Marassana WSP |
30 |
1,200 |
25 |
Connection enhancement programe in Central province |
161 |
21,000 |
NuwaraEliya District |
20 |
1,079 |
|
26 |
Proposed pipeline extension in Ginigathhena, Walapane and Maskeliya WSSs |
20 |
1,079 |
Matale District |
61 |
900 |
|
27 |
Distribution Improvement of Wilgamuwa WSP |
10 |
400 |
28 |
Distribution & Transmission of Laggala WSP |
51 |
500 |
Southern RSC |
862 |
52,500 |
|
Matara District |
862 |
52,500 |
|
29 |
Matara Stage IV Distribution Improvement Project - Phase I |
862 |
52,500 |
Sabaragamuwa RSC |
64 |
18,300 |
|
Rathnapura District |
51 |
14,300 |
|
30 |
Godakawela Distribution expansion |
15 |
1,300 |
31 |
Improvement and taking over of CBOs in Padalangala and Thorakolayaya area |
36 |
13,000 |
Kegalle District |
13 |
4,000 |
|
32 |
Distribution improvements in Ruwanwella WSS |
13 |
4,000 |
Uva RSC |
201 |
16,294 |
|
Badulla District |
153 |
11,171 |
|
33 |
Transmission and Distribution Expansion of Ettampitiya water supply project |
7 |
1,635 |
34 |
Taking over bulk water supply connection to NWSDB by doing improvement in Badulla District |
10 |
3,161 |
35 |
Distribution improvements in Demodara WSS |
136 |
6,375 |
Monaragala District |
48 |
5,123 |
|
36 |
Transmission and Distribution Expansion of Siyabalanduwa WSS |
16 |
1,090 |
37 |
Taking over of Bulk Water Supply connection to NWSDB by doing improvements in Monaragala District |
10 |
3,161 |
38 |
Taking over of Sooriyaara ( Wassip) WSS and extension to Nikawewa balance and Mahawewa area |
23 |
872 |
East RSC |
649 |
17,205 |
|
Ampara District |
532 |
14,355 |
|
39 |
Extension to Serankade Village at Padiyathalawa |
62 |
1,850 |
40 |
Infilling at Aranthalawa, Tempitiya, Borapola and Pullumalai villages in Mahaoya |
51 |
1,375 |
41 |
Infilling at Centralcamp, Gonagalla, Paragahakele & Uhana WSS |
296 |
8,400 |
42 |
Pipeline extension and infilling to Damana, Panankadu, Alikambe-Kannagikiramam & Akkaraipattu WSS |
124 |
2,730 |
Batticaloa District |
90 |
2,525 |
|
43 |
Distribution Expansion in Batticaloa District |
90 |
2,525 |
Trincomalee District |
27 |
325 |
|
44 |
Water Supply extension to Sooroyapura in Kanthale DS Division |
27 |
325 |
TOTAL |
4,634 |
235,039 |
|
Business Efficiency Improving Projects (NRW Reduction & Energy Saving ) |
1,553 |
16,693 |
|
Western South RSC |
19 |
7,664 |
|
Kalutara District |
19 |
7,664 |
|
45 |
Laying of Transmission main from Alwis Place to Wadduwa |
12 |
3,272 |
46 |
Laying of 500mm dia. DI pipe line from Kethhena WTP to Central Junction |
7 |
4,392 |
North Western RSC |
|||
Kurunegala District |
|||
47 |
Lake Side Pump Installation (Energy Project) |
||
North Central RSC |
32 |
509 |
|
Anuradhapura District |
3 |
||
48 |
Anuradhapura New Town WSS-Replacing of pumping lines of Stage II & III water towers |
3 |
|
49 |
Supply and installation of horizontal split casing pumps at Nuwarawewa WTP for Stage II & III water tower |
||
50 |
Supply & installation of Surge Vessel to Anuradhapura North WSS |
||
Polonnaruwa District |
29 |
509 |
|
51 |
Replacing of Gravity main from Minneriya (Patapilikanda Sump) to Hingurakgoda Tower |
6 |
|
52 |
Distribution line replacement of Aralaganwila WSS |
17 |
436 |
53 |
Distribution line replacement of Manampitiya WSS |
7 |
73 |
54 |
Supply and installation of surge vessel at Minneriya WTP for transmission line to Patapilikanda sump |
||
North RSC |
35 |
3,600 |
|
Jaffna District |
35 |
3,600 |
|
55 |
NRW Reduction Programmes in (Jaffna, Kilinochhci, Mullaithivu, Vavuniya & Mannar) |
35 |
3,600 |
56 |
Solar Power System for Jaffna & Vavuniya Regions |
||
Sabaragamuwa RSC |
|||
Rathnapura District |
|||
57 |
Capacitor bank-Muwagama Intake, Emblipitiya TP, Embilipitiya Intake, Kahawaththa Intake & Balangoda hospital Intake |
||
58 |
Intake Pump-Balangoda Old plant |
||
59 |
Intake Pump-Muwagama plant |
||
60 |
High lift Pump-Muwagamkanda to Samagipura plant |
||
61 |
High lift Pump- Samagipura tank to Konagoda tank |
||
62 |
Solar Power (PV) system for Ratnapura Region |
||
63 |
Intake Pump-Kahawaththa |
||
Kegalle District |
|||
64 |
Solar Power (PV) system for Kegalle Region |
||
East RSC |
1,467 |
4,920 |
|
Ampara District |
1,449 |
2,695 |
|
65 |
Replacement of PVC pipe service connection to HDPE pipe in Ampara & Akkaraipattu region |
1,217 |
1,345 |
66 |
Zoning arrangement at water supply schemes in Ampara & Akkaraipattu Region |
55 |
675 |
67 |
Replacement of Old Standard pipe (unusual diamater pipe) in the distribution system in Akkaraipattu Region |
177 |
675 |
Batticaloa District |
|||
68 |
Connection Transfer to PE and shifting meters to suitable locations in Batticaloa region |
||
Trincomalee District |
18 |
2,225 |
|
69 |
Connection Transfer to PE and shifting meters to suitable locations in Trincomalee Region |
2,025 |
|
70 |
Replacement of bundle pipe in the distribution system in Trincomalee Region |
17 |
100 |
71 |
Zoning arrangement in distribution system -Trincomalee Region |
1 |
100 |
Priority for enhancement of Revenue by Providing Connections for revenue Generating Consumer Segment |
79 |
1,637 |
|
North Western RSC |
47 |
1,450 |
|
Kurunegala District |
47 |
1,450 |
|
72 |
Distribution expansion in Kurunegala WSP |
9 |
400 |
73 |
Distribution Expansion in Thorayaya WSP |
38 |
1,050 |
North Central RSC |
6 |
2 |
|
Polonnaruwa District |
6 |
2 |
|
74 |
Water Supply to Aralaganwila Police Training School - Aralaganwila WSS |
6 |
2 |
East RSC |
26 |
185 |
|
Batticaloa District |
26 |
185 |
|
75 |
Water Supply extension to tourist areas at Passikuda in Batticaloa District |
6 |
25 |
76 |
Extension of pipe laying in tourist area Kallady, Batticaloa District |
20 |
160 |
TOTAL |
6,288 |
261,784 |
S# |
Name of the Project |
District |
WTP Capacity (m3/d) |
Length of Pipe Laying (km) |
Total New Connections (Nos.) |
Batch 1: New Projects to be implemented in year 2021 with Water treatment Plant and Intake Construction |
|||||
Western Central RSC |
5,000 |
- |
- |
||
1 |
Construction of New WTP at Awissawella |
Colombo |
5,000 |
||
Western North RSC |
40,000 |
1,631 |
42,500 |
||
2 |
Mirigama WSP - Stage I |
Gampaha |
20,000 |
778 |
20,750 |
3 |
Divulapitiya WSP - Stage I |
Gampaha |
20,000 |
853 |
21,750 |
North Western RSC |
154,000 |
3,271 |
248,020 |
||
4 |
Katupotha - Bamunakotuwa - Panduwasnuwara WSP |
Kurunegala |
20,000 |
722 |
31,700 |
5 |
Bingirya - Udubaddawa & Makadura-Pannala- Kuliyapitiya Integrated WSP - Phase I |
Kurunegala |
40,000 |
1,133 |
63,400 |
6 |
Dankotuwa WSP - Phase I |
Puttlam |
20,000 |
234 |
31,700 |
7 |
Towns North Of Kurunegala (TNK) WSP - Phase 1 |
Kurunegala |
50,000 |
254 |
78,000 |
8 |
Chilaw WSP - Stage II |
Puttlam |
12,000 |
395 |
20,160 |
9 |
Puttalam WSP- Stage II |
Puttlam |
12,000 |
533 |
20,160 |
North RSC |
50,000 |
- |
36,000 |
||
10 |
Jaffna Kilinochchi IWSP - Stage II |
Kilinochchi |
50,000 |
36,000 |
|
Central RSC |
74,500 |
1,006 |
133,840 |
||
11 |
Kundasale Haragama WSP |
Kandy |
50,000 |
357 |
91,300 |
12 |
Nanuoya WSP |
Nuwara Eliya |
2,000 |
72 |
4,525 |
13 |
Hapugasthalawa WSP |
Nuwara Eliya |
7,500 |
135 |
10,313 |
14 |
Delthota WSP |
Kandy |
5,000 |
122 |
6,930 |
15 |
Medadumbara Panwila WSP |
Kandy |
10,000 |
321 |
20,735 |
Southern RSC |
105,000 |
935 |
102,300 |
||
16 |
Greater Galle WSP - Stage III |
Galle |
50,000 |
387 |
54,300 |
17 |
Baddegama IWSP-Stage I |
Galle |
30,000 |
217 |
28,000 |
18 |
Lunugamwera IWSP - Phase I & II |
Hambanthota |
25,000 |
331 |
20,000 |
Sabaragamuwa RSC |
55,500 |
393 |
56,403 |
||
19 |
Kiriella WSP |
Rathnapura |
3,000 |
34 |
4,740 |
20 |
Embilipitiya Paper Mill WSP |
Rathnapura |
30,000 |
20,325 |
|
21 |
Balangoda WSP - Stage II |
Rathnapura |
7,500 |
258 |
10,363 |
22 |
Eheliyagoda WSP |
Rathnapura |
15,000 |
102 |
20,725 |
Uva RSC |
50,000 |
1,271 |
54,092 |
||
23 |
Bandarawela WSP - Phase I &II |
Badulla |
20,000 |
651 |
23,183 |
24 |
Badalkumbura WSP |
Monaragala |
5,000 |
77 |
5,215 |
25 |
Bibila Medagama WSP - Phase ll |
Monaragala |
5,000 |
149 |
6,955 |
26 |
Hambegamuwa WSP |
Monaragala |
4,000 |
138 |
4,057 |
27 |
Loggaloya WSP |
Badulla |
4,000 |
102 |
3,091 |
28 |
Wellawaya WSP - Stage II phase Il |
Monaragala |
12,000 |
156 |
11,591 |
East RSC |
39,000 |
384 |
54,225 |
||
29 |
Morawewa & Gomarankadawala WSP |
Trincomalee |
4,000 |
303 |
5,100 |
30 |
Greater Trincomalee Expansion WSP |
Trincomalee |
20,000 |
30 |
25,500 |
31 |
Valachchenai WSP |
Batticaloa |
15,000 |
51 |
21,125 |
Sub Total 1 |
573,000 |
8,891 |
725,280 |
||
Batch 1: New Projects to be implemented in 2021 with Pipe Laying and Other Works |
|||||
Western Central RSC |
- |
351 |
- |
||
32 |
Upgarading Water Supply Facilities in Jubilee Kotte Area |
Colombo |
133 |
- |
|
33 |
Upgarading Water Supply Facilities in Kolonnawa Area |
Colombo |
219 |
- |
|
Western North RSC |
497 |
77,000 |
|||
34 |
Infilling work of KRB Project Stage II in Kelaniya Region |
Gampaha |
497 |
77,000 |
|
Western South RSC |
- |
296 |
26,000 |
||
35 |
Ingiriya - Hadapangoda WSP |
Kaluthara |
296 |
26,000 |
|
36 |
Construction of Salinity Barrier - Kalu Gaga |
Kaluthara |
- |
||
North Western RSC |
- |
248 |
7,950 |
||
37 |
Melsiripura WSP |
Kurunegala |
123 |
3,975 |
|
38 |
Extension to Rasnayakapura |
Puttlam |
125 |
3,975 |
|
North RSC |
- |
38 |
850 |
||
39 |
Chunnakam WSP |
Jaffna |
38 |
850 |
|
Central RSC |
- |
758 |
51,304 |
||
40 |
Greater Matale WSP - Stage II |
Mathale |
758 |
51,304 |
|
Sub Total 2 |
- |
2,188 |
163,104 |
||
TOTAL- Batch 1 |
573,000 |
11,079 |
888,386 |
||
Batch 2: New Projects to be implemented in year 2022-2023 with Water treatment Plant and Intake Construction |
|||||
Western Central RSC |
180,000 |
- |
|||
41 |
Weliwita WSP - Head Works (Stage-1) |
Colombo |
180,000 |
- |
|
Western North RSC |
57,000 |
969 |
69,400 |
||
42 |
Kiridiwela WSP – Stage I |
Gampaha |
30,000 |
419 |
40,000 |
43 |
Gampaha Attanagalla Minuwangoda WSP - Stage II |
Gampaha |
27,000 |
550 |
29,400 |
Western South RSC |
50,000 |
600 |
80,000 |
||
44 |
Kethhena Improvement & Expansion Project |
Kaluthara |
50,000 |
600 |
80,000 |
North Western RSC |
22,000 |
- |
34,760 |
||
45 |
Kalpitiya WSP |
Puttlam |
12,000 |
18,860 |
|
46 |
Galgamuwa - Ehatuwewa - Ambanpola WSP |
Kurunegala |
10,000 |
15,900 |
|
North Central RSC |
64,000 |
3,474 |
99,284 |
||
47 |
Anuradhapura South WSP - Phase II |
Anuradhapura |
10,000 |
257 |
12,856 |
48 |
Palugaswewa WSP |
Anuradhapura |
5,000 |
355 |
6,428 |
49 |
Towns East of Polonnaruwa WSP |
Polonnaruwa |
48,000 |
2,862 |
80,000 |
North RSC |
2,750 |
74 |
2,600 |
||
50 |
Kankesanthurai WSS- Stage 1 |
Jaffna |
1,000 |
21 |
850 |
51 |
Chulipurm WSS-Stage 1 |
Jaffna |
750 |
48 |
1,250 |
52 |
Point Pedro & VVT (RO Plant) WSS |
Jaffna |
1,000 |
5 |
500 |
Central RSC |
48,500 |
910 |
60,616 |
||
53 |
Hasalaka WSP |
Kandy |
7,500 |
208 |
13,200 |
54 |
Pundaluoya WSP |
NuwaraEliya |
5,000 |
72 |
6,880 |
55 |
Hatharaliyadda WSP |
Kandy |
5,000 |
111 |
6,963 |
56 |
Nawalapitiya Pallegama WSP |
Kandy |
2,000 |
58 |
2,750 |
57 |
Pupuressa Atabage WSP |
Kandy |
10,000 |
148 |
12,430 |
58 |
Ganga Ihala Korale WSP |
Kandy |
10,000 |
150 |
10,450 |
59 |
Naula Wahakotte WSP |
Mathale |
4,000 |
80 |
5,193 |
60 |
Kothmale River Side WSP |
Kandy |
5,000 |
83 |
2,750 |
Southern RSC |
98,000 |
521 |
98,300 |
||
61 |
Imaduwa WSP |
Galle |
6,000 |
64 |
7,300 |
62 |
Kataragama Long term -Phase I &II |
Hambanthota |
15,000 |
106 |
5,600 |
63 |
Ruhunupura - Stage II |
Hambanthota |
20,000 |
42 |
10,000 |
64 |
Augmentation of Hakmnana WSS |
Mathara |
7,500 |
11 |
9,000 |
65 |
Deniyaya WSP |
Mathara |
6,000 |
156 |
7,400 |
66 |
Morawaka WSP |
Mathara |
6,000 |
142 |
8,500 |
67 |
Mathara - Stage V |
Mathara |
30,000 |
42,500 |
|
68 |
Deyyandara-Mulatiyana WSP |
Mathara |
7,500 |
0 |
8,000 |
Sabaragamuwa RSC |
82,000 |
317 |
119,030 |
||
69 |
Doloswala, Nivithigala, Karavita WSP |
Rathnapura |
5,000 |
0 |
6,855 |
70 |
Dehiowita WSP |
Rathnapura |
15,000 |
0 |
23,600 |
71 |
Kuruvita WSP |
Rathnapura |
5,000 |
18 |
6,975 |
72 |
Kalawana WSP |
Rathnapura |
5,000 |
106 |
5,380 |
73 |
Warakapola WSP |
Kegalle |
15,000 |
193 |
15,800 |
74 |
Integration of Kegalle WSS |
Kegalle |
10,000 |
0 |
20,200 |
75 |
Rambukkana WSP |
Kegalle |
15,000 |
0 |
24,600 |
76 |
Greater Rathnapura WSP - Stage II |
Rathnapura |
18,000 |
17,500 |
|
Uva RSC |
73,500 |
6,277 |
81,506 |
||
77 |
Gawarammana Bogahakumbura WSP |
Badulla |
15,000 |
173 |
16,227 |
78 |
Yahalarawa WSP |
Badulla |
2,000 |
48 |
2,319 |
79 |
Ulhitiya WSP |
Badulla |
4,000 |
136 |
3,477 |
80 |
Thaldena Meegahakiula WSP |
Badulla |
5,000 |
68 |
4,057 |
81 |
Welimada Stage II |
Badulla |
4,000 |
101 |
2,319 |
82 |
Thanamalvila Sevanagala IWSP |
Monaragala |
10,000 |
5,750 |
1,932 |
83 |
Springvelly WSP |
Badulla |
2,000 |
2,750 |
|
84 |
Haldummulla WSP |
Badulla |
1,500 |
1,738 |
|
85 |
Greater Monaragala WSP |
Monaragala |
30,000 |
49,050 |
|
East RSC |
18,500 |
205 |
17,675 |
||
86 |
Water supply Improvements in Muthur East area |
Trincomalee |
10,000 |
52 |
12,750 |
87 |
Lahugala WSP |
Ampara |
1,000 |
1,310 |
|
88 |
Dehiyaththakandiya WSP |
Ampara |
7,500 |
153 |
2,415 |
Sub Total 1 |
696,250 |
13,346 |
663,171 |
||