Project Name District Type of Project No. of Beneficiaries Duration Total Estimated Cost (Rs. million) Actual Expenditure as at end 2010 (Rs. million) Physical Progress %
From To
Central Province
Matale WS Matale Augmentation 15,000 Jan 1999 Apr 2014 384.9 347.85 90
Kundasale Integrated WS - Stage II Kandy Augmentation 130,000 Jan 1998 Dec 2014 1,400.00 1,276.73 85
Marassana WS Kandy New 25,000 Jan 1996 Dec 2014 222 282.12 95
Thalawakele/ Lindula WS Nuwara Eliya Augmentation 15,000 Jan 2000 Dec 2014 172 188.69 90
Palapathwela WS Matale Extension 22,000 Jan 2000 Dec 2014 150 159.15 80
North Central Province
Hingurakkoda WS Polonnaruwa Augmentation 6,000 Jan 1996 Dec 2015 130 124.94 98
Minneriya WS - Stage II Polonnaruwa Augmentation 69,000 Jan 2007 Dec 2015 100 102.58 97
Medirigiriya WS - Stage I Polonnaruwa New 60,000 Jan 2007 Dec 2015 638 574.66 70
Mahanelubewa WS Anuradhapura New   Dec 2010 Dec 2014 129.7 113.74 97
Ippalogama Housing Scheme WS Anuradhapura Extension 18,000 Jan 2007 Dec 2014 798 598.12 92
Parasangaswewa Anuradhapura New 1,000 Jan 2013 Dec 2013 31.6 -  
Deyata Kirula       Jan 2011 Dec 2012 830 528.67 85
Eastern Province
Kantale WS Trincomalee Augmentation 25,000 Jan 1999 Dec 2012 274.8 216.37 69
Tampalakamam WS Trincomalee Augmentation 30,000 Jan 1999 Dec 2011 95.2 85 100
Transmission Main from Kantale to Tampalakamam Trincomalee     Jan 2012 Jan 2014 1,397.80 450 80
Wadinagala/ Wan - Ela WS       Jan 2012 Dec 2015 808.5 19.04 10
Serunuwara WS Trincomalee Augmentation 9,500 Jan 2001 Dec 2013 110.1 106.28 48
Dehiattakandiya WS - Stage I & II Ampara Augmentation 16,000 Jan 2007 Dec 2012 300 250.74 99
Deyata Kirula 2013 Ampara, Trincomalee     Jan 2012 Dec 2013 1,875.00 26.89  
Northern Province
Wastewater Treatment Plant for Kilinochchi Hospital       Jan 2012 Dec 2012 36 6.95  
Mahawa/ Wariyapola/ Nikaweratiya WS       Jan 2012 Dec 2014 505 40.7 90
North Western Province
Ibbagamuwa WS       2012 Dec 2014 239 62.02 4
Divulagane WS Kurunegala New 1,950 Jan 2013 Oct 2015 46.7 -  
Dambadeniya       Jan 2012 Dec 2016 796 3.26 2
Mahawa/ Wariyapola/ Nikaweratiya WS Kurunegala Augmentation 45,000 Jan 2000 Dec 2014 996.7 856.31 89
Sabaragamuwa Province
Embilipitiya WS Ratnapura Augmentation 84,000 Sep  2003 Dec 2013 363 387.88 94
Pelmadulla WS Ratnapura Augmentation 14,500 Jan 2000 Dec 2015 384.2 355.47 96
Nivithigala WS Ratnapura Augmentation 14,500 Jan 1999 Dec 2013 99.1 70.01 58
Udawalawa WS Stage I & II Ratnapura Augmentation 9,400 Jan 1999 Dec 2014 973.6 654.59 90
Yatiyantota WS Kegalle Augmentation 9,400 Sep 2003 Dec 2012 165.8 176.6 85
Godakawela WS Ratnapura Augmentation 22,500 Jan 1999 Dec 2011 288.8 211.63 98
Pattampitiya WS Kegalle Extension 7,300 Jan 2001 Dec 2011 145.2 143.61 100
Galigamuwa WS Kegalle New 30,800 Jan 2011 Dec 2014 841 219.11 36
Madola WS Kegalle New 4,500 Jan 2013 Dec 2013 132 -  
Kiriella WS Ratnapura   7,300 Jan 2011 Dec 2014 205 21.92 97
Southern Province
Akuressa WS Matara New 15,000 Jan 1999 Dec 2011 338.6 272.66 100
Thihagoda WS Matara New 7,500 Jan  2001 Dec 2011 162.1 172.46 100
Baddegama WS Galle New 33,830 Jul 2013 Aug 2015 441    
Gonapinuwala WS Galle New 20,825 Jul 2013 Aug 2015 350    
Dikkumbura WS Galle New 17,130 Jul 2013 Aug 2015 275    
Bentota WS Galle New 18,850 Jul 2013 Aug 2015 700    
Udugama WS Galle New 6,000 Apr 2001 Dec 2011 145.5 139.51 100
Pitabeddara WS Matara New 6,000 Jan 2001 Dec 2011 130.3 102.5 98
Bonavista Kanda Area WS Matara   600 Jan 2010 Dec 2012 57 44.03 99
Hakmana WS Matara   10,000 Jan 2008 Dec 2013 383.4 123.76 60
Uva Province
Ohiya Transmission Badulla New 10,000 Feb 1999 Dec 2013 264.7 206.23 96
Monaragala WS - Stage II Monaragala New 10,000 Jun 1999 Dec 2013 154.8 142.17 98
Badalkumbura WS Monaragala New 22,000 Oct 1999 Dec 2013 124.4 97.18 86
Buttala WS Monaragala   2,600 Jan 2010 Dec 2012 295 287.44 100
Ambagasduwa WS Badulla New 6,000 Jun 1999 Dec 2013 382 137.22 72
Wellawaya WS Monaragala Augmentation 6,000 Jan 2007 Dec 2014 250 96.81 65
Western Province
Rehabilitation of Western Central WS Colombo Rehabilitation 162,500 2009 Dec 2012 1,300.00 1,317.51 97
Kirindiwela WS Gampaha New 8,000 May 1998 Dec 2013 198 172.63 90
Nittambuwa/ Veyangoda WS Gampaha Augmentation 15,000 Oct 1999 Dec 2013 210.7 201.96 96
Kalutara Integrated WS - Stage II Kalutara Augmentation 210,000 Jan 2008 Dec 2014 1,366.20 789.16 58
Jalthara - Ranala WS Colombo   17,920 Jan 2010 Dec 2013 217.2 86.15 27
Katunayake WS - Stage WS 1 & II Gampaha Augmentation 29,000 Jan 2005 Dec 2014 470 265.03 62
Kolonnawa Sewerage Colombo New 20,000     1,296.00 -  
Inter Provincial Projects/ Programmes
Small Schemes & Disaster Management Programme and Urgent Improvements (TCE Less than Rs.10 M )
a. Madola
b. PahalaKaduganna
c. Eheliyagoda
d. Extension to Batuwatta & Kopparamessa
e. Menikdola
f. Kabagamuwa
g. Makurakanda
h. Ellawala
    10,000 Jan 2010 Dec 2012 92.5 88.9  
Investigations, Surveys & Feasibility Studies for new project proposals           100 12.55  
Utility shiffting / replacement owing to accelerated Pradeshiya Sabha Road Development Programmmes           300 25.05  
* Abbreviations
 WS :  Water Supply

 Emerging small townships Water Supply Projects Click here.....

 

 

Name  
ADB V(a) Click here.....
         (b) Click here....
         (c) Click here.....
Ampara JICA Click here.....
Ampara Phase III Click here.....
Anuradhapura Click here.....
Badulla Click here.....
CWSSP Click here.....
Dambulla Click here.....
GColombo Click here.....
Jaffna Click here.....
Kalatuwawa Click here
Kalu Ganga Click here.....
Kilinochchi Click here.....
Kolonna Click here.....
Mahiyangana Click here.....
Monaragala Click here.....

 

Project Name (Donor) District Type of Project No. of Beneficiaries Duration Total Estimated Cost (Rs. million) Actual Expenditure as at end 2010 (Rs. million) Physical Progress %
From To
Central Province
Water Sector Development Project 1 Sub Project 4 Greater Kandy WS Phase I Stage II (JICA) Kandy Augmentation 616,000 Oct 2007 Jul 2012 4,164.00 4,681.63 94
Greater Dambulla WS - Stage 1 (INDIA) Nuwara Eliya Augmentation   2012 Jul 2014 9,593.00 5,808.50 23
Eastern Province
Eastern Coastal Towns of Ampara District (ECTAD) WS Phase II (Australia) Ampara New 161,400 Oct 2002 Dec 2010 11,078.20 10,712.13 100
Eastern Province Water Supply Development Project (JICA) Ampara New   2010 2015 6,526.00 1,407.16 70
Integrated Water Supply Scheme for the Unserved Area of Ampara District Phase III (Australia) Ampara New 80,000 2007 2015 18,012.00 9,904.30 36
Northern Province
Jaffna Killinochchi Water Supply & Sanitation (ADB VI) Jaffna Augmentation 15,000 2011 2016 18,328.20 194.56 15
Killinochchi Rehabilitation Water Supply Project (JICA)     15,000 2013 2015 1,900.00 -  
Immediate Arragements to provide Water Supply to Kilinochchi (New 2 KR) (JICA )       2013 2015 260 150 65
North Central Province
Thambuttegama WS (China) Kurunegala New   2014 2017 1,805.00 -  
Anuradhapura North Intergrated Water Supply (JICA)       2013 2015 9,736.00 -  
Southern Province
Ruhunupura WS Development (Korea)       Jan 2011 Mar 2013 13,131.30 5,378.20 46
Kirama, Katuwana, Middeniya & Angunakolapelessa Integrated WS (China) Galle Augmentation 160,000 Jan 2012 Jan 2013 2,662.00 -  
Rehabilitation & Augmentation of Kirindioya Water Supply (Austria) Hambantota Augmentation 30,000 Feb 2007 Dec 2009 2,104.83 1,914.25 100
Uva Province
Badulla - Haliela and Ella Integated WS (US Exim Bank)       2013 2015 10,396.50 5.1  
Mahiyangana Water Supply (Austria)       2013 2016 1,785.00 -  
Western Province
Water Sector Development Project I
Towns North of Colombo WS -stage II (JICA)
Colombo Extension 200,000 2007 2014 6,490.00 5,750.36 97
Kelani Right Bank WTP (DANIDA) Colombo New 1,500,000 Oct 2008 Dec 2013 12,000.00 9,477.31 98
Rehabilitation & Augmentation of Labugama - Kalatuwawa WTP (Hangary) Colombo Rehabilitation 375,000 2013 2016 8,100.00 1.29 -
Augmentation of Negombo WS (DUTCH) Gampaha Augmentation 137,500 2008 2013 7,302.00 6,703.69 98
Water Sector Development Project I
Greater Colombo Water Rehabilitation (JICA)
Colombo Rehabilitation 100,000 2007 2015 4,785.00 3,476.78 74
Water Sector Development Project II (JICA)
Kaluganga Water Supply Project Phase I -Stage II & Non Revenue Water Reduction in Colombo City (NRW Master Plan)
      Jul 2008 Dec 2015 10,846.00 4,650.60 66
Consultancy Services for Non Revenue Water (NRW) Engineering Study, Master Plan Update and Institutional Development       Oct 2011 Jun 2013 412.1 -  
Energy Conservation Project at Ambatale WTP (GERMAN)       2012 2014 6,220.00 -  
Capacity Development Project for NRW reduction in Colombo City (JICA)       2010 2011 201 30.6 100
Colombo Water Supply Service Improvement Project (ADB)       2012 2018 28,800.00 8.12  
Katana WS (China)       2014 2015 1,641.00 -  
Water Treatment Facilities Moratuwa / Panadura, Ambatale and in Negombo (Spanish) [formerly Galagoda WSS] Colombo, Gampaha New 10,000 Oct 2007 Dec 2009 2,690.00 2,672.34 100
Sabaragamuwa Province
Greater Ratnapura Water Supply Project (Spain)       Jan 2012 Dec 2016 9,928.00 -  
Kolonna/ Balangoda Water Supply Project (Belgium)       2011 2015 4,658.00 1,244.50 5
North Western Province
Greater Kurunegala (China)       Jan 2013 Dec 2015 11,943.00 -  
Wandura Pinu Ella WS (China)       Jan 2012   9,756.00 -  
Inter Provincial Projects/ Programmes
Secondary Towns Rural Community Based WS & Sanitation (ADB 4th project) Polonnaruwa, Anuradhapura, Trincomalee, Hambantota, Batticaloa New 968,000 (Water) & 171,500 (Sanitation) Jan 2004 2013 29,680.00 25,692.94 95
Dry zone urban Water & Sanitation Project(ADB V)     86,000 Jun 2009 Jun 2014 13,029.60 1,494.19 31
Hambantota/ Ambalantota/ Weligama/ Kataragama Implementation Project & Badulla, Bandarawela Integrated Feasibility Studies (UNIHA) Hambantota, Matara Augmentation 150000 & SLI 200,000 Nov 2004 Dec 2013 2,126.00 1,767.88 98
* Abbreviations
ADB : Asian Development Bank
DANIDA : DANish International Development Agency
JICA : Japan International Cooperation Agency
KfW : Credit for Reconstruction
SLI : Service Level Improvements
UNICEF : United Nations International Children's Fund
WS : Water Supply
Project Name District No. of Beneficiaries Duration Total Estimated Cost (Rs. million) Actual Expenditure as at end 2010 (Rs. million)
From To
Water Sanitation & Hygine Programme (WASH program) Mulaitivu, Ampara, Hambantota, Kalutara, Tangalle & Thirukkovil   2011 2013 240 141.57
Tsunami Affected Areas Rebuilding Fund Project - Component D (ADB) Trincomalee, Batticaloa & Hambantota 14253 families 2,005 2011 1,230.00 919.78
Assistance for Emergency Measures and Ambalangoda WSS (KfW) Galle   2,007 2011 4,201.70 4,898.52
Trincomalee Integrated Infrastructure Project (French Development /Agency - AFD-Component 2) Trincomalee   2006 2013 2,819.30 1,983.18
IFRC Funded Tsunami Transmission System Improvement (IFRC) Jaffna, Ampara, Hambantota, Matara & Galle   2005 2011 3,785.00 2,422.16
Greater Trincomalee Integrated Water Supply (RPE France) Trincomalee   2,006 2013 2,881.00 2,011.17
* Abbreviations
ADB : Asian Development Bank
IFRC : International Federation of Red Cross
KfW : Reconstruction Credit Institute
UNICEF : United Nations International Children's Fund
USAID : United States Agency for International Development

 


Project Name District Type of Project No. of Beneficiaries Duration Total Estimated Cost (Rs. million) Actual Expenditure as at end 2010 (Rs. million) Physical Progress %
From To
Central Province
Water Sector Development Project 1 Sub Project 1
Sewage disposal system for Kandy Municipal area (JICA)
Kandy New 49,700 Oct 2007 Dec 2017 22,585.00 797.99 3
Southern Province
Galle Sewerage (China) Galle     2010 2014 3,200.00 -  
Kataragama Sacred City Waste Water Disposal Monaragala Augmentation 15,000     615.0    
Western Province
Rehabilitation & Upgrading of Southern Catchments of GC Sewerage (Austrian) Colombo Rehabilitation 300,000 2007 2010 2,222.00 1,881.87 100
Waste Water Disposal System for Ratmalana/ Moratuwa & Ja-Ela/ Ekala Areas (SIDA) Colombo New 94,500 2008 2013 16,155.00 12,695.26 85
Greater Colombo Waste Water Managemet (ADB) Colombo Rehabilitation 500,000 2010 2014 1,012.00 36.98 2
GPOBA funded project for increasing Household Access to Sewerage Services (World Bank)       2012 2014 1,095.00 3.06  
Maharagama Boralesgamuwa (China)       2013 2015 2,200.00 -  
Hospital Sewerage System Improvement (China)       2012   2,100.00 -  
North Western Province
Greater Kurunegala Water Supply & Sanitation Kurunegala Augmentation/ New 64,000     8,283.0    
* Abbreviations
ADB : Asian Development Bank
DANIDA : DANish International Development Agency
JICA : Japan International Cooperation Agency
SIDA : Swedish International Development Cooperation Agency
WS : Water Supply

 

Global partnership on Output Based - Aid project is implementing under the funds from World Bank, GOSL, NWSDB. Main objectives of the project are to increase house hold Access to domestic sanitation in Greater Colombo for low income households.

It is targeted to give 8800 hoseholds sanitation facilityes and it will be benefited for 44000 people in Dehiwala/Mt. Lavinia, Kolonnawa, Moratuwa and Jaela/Ekala area.

Details of GPOBA Project and SPEARs  
Spear Badovita  Download
Spear DC   Download
Spear Diyawarapura   Download
Spear Lunawa  Download
Spear On-Site  Download
Spear SCE Stage  Download
Spear Tsunami  Download

THE GOVERNMENT OF THE DEMOCRATIC SOCIALIST REPUBLIC OF SRI LANKA
MINISTRY OF CITY PLANNING AND WATER SUPPLY
NATIONAL WATER SUPPLY AND DRAINAGE BOARD

Date : 08/02/2017

Loan No. & Title : ADB Loan No. 3030-SRI;
AFD Loan No.:- CLK 1008 – 01P AFD Credit Facilities
Greater Colombo Water and Wastewater Management Improvement Investment Programme - Project 2;
AFD Contractual Co Financing - Ambathale Water Supply System Improvement & Energy Saving Project

Contract No. : GCWWMIIP/AFD/EQUIP/OPER/ICB/06

Title :Bidding Document for Machinery and Equipment for Operation and Maintenance Activities of Western Production Section

Deadline for Submission of Bids: 29/03/2017, 10:00 hours (Local time)

Please refer the attached IFB for more details.Click here.....
 

 

 

Write comment (0 Comments)

 

No

Project

WTP Capacity (m3/d)

New Connections (Domestic) Nos.

Expected Date of Completion

Foreign Financing

1

Polgahawela, Pothuhera and Alawwa Integrated Water Supply project

29,000

32,500

Apr-21

2

Kelani Right Bank WSP

180,000

17,500

Oct-20

3

Greater Matale WSP

75,000

20,000

Dec-20

4

Gampaha, Attanagalla & Minuwangoda Integrated Water Supply Scheme

54,000

18,975

Dec-22

5

Aluthgama, Mathugama and Agalawatta Integrated Water Supply Project

74,250

29,000

Apr-21

6

Matara Stage IV WSP

30,000

9,000

Mar-22

7

Thambuttegama WSP

18,000

25,000

Dec-22

8

Katana WSP

 

22,000

Nov-20

9

Replacing of Transmission and Distribution Mains from Orugodawatta to Kaduwela Project

-

-

Dec-21

10

Hemmathagama Water Supply Project

21,000

14,400

Jun-22

11

Deduru Oya Water Supply Project

15,000

14,750

Nov-20

12

Anamaduwa Integrated Water Supply Project

11,000

6,450

Nov-21

13

Kandy North Pathadumbara Integrated Water Supply Project

50,000

41,000

Nov-22

14

Kirama Katuwana Integrated Water Supply Project

3,500

3,850

Aug-21

15

Dry Zone Urban Water & Sanitation Project

   

Jul-20

16

Jaffna Kilinochchi Water Supply &
sanitation Project

24,000

60,000

Sep-23

17

Colombo Water Supply service Improvement Project 1 (Package 1)

   

Dec-20

18

Colombo Water Supply service Improvement Project 1 (Package 2)

   

Sep-21

19

Colombo Water Supply service Improvement Project 2 (Package 3 and Package 4)

   

Dec-22

20

Ambatale Water Supply System Improvement & Energy Saving Project

   

Dec-22

21

Anuradhapura North Water Supply Project - Phase 1

9,400

9,428

Mar-21

22

Anuradhapura North Water Supply Project Phase II

17,500

25,000

Dec-24

23

Kalu Ganga Water Supply Expansion Project (1)

140,000

185,000

Dec-25

24

Ruwanwella Water Supply project

4,000

4,800

Jun-22

Local Financing Projects

25

Towns East of Colombo (Package 1) WSP

   

Feb-20

26

Towns East of Colombo (Package 2) WSP

   

Dec-20

27

Towns East of Colombo (Package 3) WSP

 

32,000

Aug-20

28

Wilgamuwa WSP

5,500

6,375

Dec-20

29

Laggala WSP

4,000

5,125

Mar-21

30

Galageddara Mawathagama WSP

 

7,140

Aug-20

31

Medirigiriya WSP

 

4,500

Jul-20

32

Galle Cluster WSP

 

12,505

Nov-20

33

Attampitiya WSP

3,000

700

Feb-21

34

Greater Rathnapura WSP

 

5,950

Dec-20

35

Giridara WSP

 

4,500

Dec-20

36

Second Phase of the Pipe Laying Project from Andaragasyaya underground tank to Gannoruwa in Hambantota District

 

2,800

Dec-20

37

Thissamaharmaya WSS

 

2,000

Dec-20

38

Water Supply Facilities for Resettlement Villages in Kegalle District

 

800

Jul-21

39

Augmentation of Trincomalee Water Supply Scheme

   

Dec-21

40

Madhu Church Water Supply Scheme  

 

2,900

Dec-21

41

Project for Enhancement of Operational Efficiency and Assets Management Capacity of RSC (Western South) NWS&DB)

   

Jun-21

42

Matara Short Term Improvements

 

5,000

Dec-21

43

Bandarawela WSS improvement project

 

2,500

   Aug-20

44

Dankotuwa WSS

 

4,590

May-21

             

 

Project Name

Water Source

Production Increase (m3/day)

Approval

Length of Pipe Laying (km)

 

Western Central RSC

553,000

53,000

4,250

 
 

Colombo District                                       

553,000

53,000

4,250

 

1

Ambatale Water Treatment Plant Expansion Project

550,000

50,000

   

2

Improvement of Awissawella Water Treatment Plant

3,000

3,000

4,250

 
 

Western North RSC

32,750

15,750

19,275

12

 

Gampaha District

32,750

15,750

19,275

12

3

Augmentation of Gampaha WTP

3,500

2,000

2,500

 

4

Augmentation of Divulapitiya WTP

1,250

1,750

1,875

 

5

Rehabilitation of Raddolugama WSS

7,000

2,000

2,500

 

6

Extension of Intake Structure at Pugoda

6,000

     

7

Augmentation of Ranpokunawatta WTP

6,000

4,000

4,900

12

8

Augmentation of Veyangoda WSS

3,000

2,000

2,500

 

9

Augmentation of Yakkala WSS

3,000

2,000

2,500

 

10

Augmentation of Nittambuwa WSS

3,000

2,000

2,500

 
 

Western South RSC

120,550

11,000

11,000

1

 

Kalutara District

120,550

11,000

11,000

1

11

Ingiriya Water Supply Improvement Project

550

1,000

1,000

 

12

Capacity Improvement of Kadana WTP

120,000

10,000

10,000

 
 

North Western RSC

6,100

1,800

3,886

20

 

Kurunegala District

500

500

500

3

13

Mawathagama Water Supply Project

500

500

500

3

 

Puttalam District

5,600

1,300

3,386

17

14

Nattandiya - Wennappuwa Water Supply Scheme

1,100

400

1,886

9

15

Kakkapalliya Water Supply Project

4,500

900

1,500

8

 

North Central RSC

66,500

50,500

39,305

324

 

Anuradhapura District

38,000

18,500

21,645

88

16

Augmentation of Thissawewa WTP

4,500

4,500

4,668

50

17

Augmentation of Thuruwila WTP

18,000

4,500

5,628

 

18

Construction of a 5,000m3/day capacity WTP at Galnewa

2,000

5,000

4,840

1

19

Kalawewa WSS Improvements

13,500

4,500

6,509

37

 

Polonnaruwa District

28,500

32,000

17,660

237

20

Improvements to Minneriya WTP & WSS

9,000

4,500

3,588

1

21

Augmentation of Polonnaruwa Old WTP

6,000

500

0

11

22

Augmentation of Gallella WTP

13,500

18,000

1,572

 

23

Medirigiriya WTP -Phase 2

-

9,000

12,500

225

 

North RSC

24,855

19,817

31,540

235

 

Jaffna District

10,270

3,120

6,725

76

24

Augmentation of Delft WSS

100

100

350

18

25

Service Level Improvement in Naranthanai WSS

-

100

825

10

26

Improvement to Existing Water Supply Schemes in Thaiyaddi & Vadakkachchi

170

740

1,250

45

27

Improvement of WTP in Thottaveli, Murunkan & Point Pedro

 

2,180

4,300

3

 

Kilinochchi District

 

7,600

9,815

58

28

Improvement to Existing WTP at Kilinochchi

 

3,800

4,000

 

29

Improvement to Akkarayan WSS

   

800

 

30

Paranthan to Palai Transmission Main

   

2,200

25

31

Groundwater Source Development in Northern region

 

3,800

2,815

33

 

Mannar District

 

1,147

4,400

84

32

Rehabilitation of Thalai Mannar WSS

 

900

1,800

49

33

Service level Improvement in Musali Water supply scheme

 

247

2,600

35

 

Mullaitivu District

 

1,200

3,700

18

34

Service Level Improvement in Mankulam Water supply scheme

   

700

 

35

Augmentation of Oddusuddan & Nedunkerney WSS (stage 1 & 2)

 

600

1,500

 

36

Augmentation of Pandiankulam & Mallavi WSS

 

600

1,500

18

 

Vavuniya District

 

6,750

6,900

 

37

Peraru Bund raising for additional 0.8MCM

 

6,000

4,400

 

38

Service Level Improvement in Cheddikulam WSP

 

750

1,500

 

39

Improvement to Omanthai WSS

   

1,000

 
 

Central RSC

 

11,500

7,000

21

 

Kandy District

 

11,500

7,000

21

40

Installation of 1500m3/day package TP for Medadumbara WSS & Pipe Laying

Kota Ganga

1,500

 

18

41

Augmentation of Balagolla WTP

 

6,000

3,500

 

42

Augmentation of Marassana WTP

 

4,000

3,500

3

 

Southern RSC

 

67,900

47,600

228

 

Galle District

 

9,000

6,300

57

43

Capacity improvement and distribution expansion project of Baddegama WSS

 

6,000

3,000

30

44

Capacity improvement and distribution expansion project of Pitigala WSS

 

1,000

1,000

3

45

Capacity improvement and distribution expansion project of Udugama WSS

 

2,000

2,300

25

 

Hambanthota District

 

53,000

35,500

169

46

Capacity improvement and distribution expansion project of Lunugamwehera WSS Phase I & II

 

6,000

3,000

12

47

Capacity improvement and distribution expansion project of Kataragama WSS (Short Term)

 

9,000

6,500

34

48

Barawakumbuka short term Phase I

 

6,000

 

5

49

Barawakumbuka short term Phase II

   

5,000

49

50

Nawayalawila source Improvement Project of Tangalle WSS

 

6,000

4,000

 

51

Augmentation of Muruthawela WSS and Distribution Expansion

 

6,000

5,000

23

52

Augmentation of Kattakaduwa WTP and distribution expansion project of Ranna WSS

12,000

12,000

6,000

 

53

Construction of 6,000 m3/day capacity WTP and Transmission and Distribution expansion for Wakamulla WSS (Phase 1)

1,200

6,000

5,000

1

54

Wakamulla WSS (Phase 2)

   

0

43

55

Augmentation of Bundala WSS

300

1,000

500

2

56

Augmentation of Katuwana WSS

800

1,000

500

 
 

Matara District

9,085

5,900

5,800

3

57

Augmentation of Hallala WSS

8,000

3,000

3,000

 

58

Capacity Enhancement & Distribution Expansion project of Hakmana WSS

900

900

300

3

59

Capacity improvement and distribution expansion project of Urubokka WSP

185

2,000

2,500

 
 

Sabaragamuwa RSC

52,400

32,100

23,220

159

 

Kegalle District

39,900

22,100

12,820

41

60

Integration of Kegalle WSS

8,500

2,500

1,500

 

61

Upgrading Moronthota WTP and associated Transmission and Distribution System improvements

11,250

6,750

-

3

62

Upgrading Mawanella WTP and associated Transmission and Distribution System improvements

15,000

3,000

3,000

12

63

Supply and laying of gravity transmission main to Adurapotha tank

 

-

-

5

64

Improvements of the Intake weir of Yatiyanthota Water Treatment Plant

950

1,050

1,320

 

65

Upgrading Dehiowita WTP & Distribution Improvements

1,000

2,000

2,500

12

66

Upgrading existing Ruwanwella water treatment plant

2,000

4,000

2,000

 

67

Upgrading existing Warakapola WTP & Distribution Improvements

1,200

2,800

2,500

9

 

Rathnapura District

12,500

10,000

10,400

118

68

Upgrading Pelmadulla WTP & Distribution Improvements

3,000

1,500

3,000

29

69

Augmentation of old Balangoda WTP & Laying of DI pumping main

3,000

4,000

2,000

1

70

Construction of Intake at Thalavitiya, Raw water transmission and Aerator for improving quality of service in Eheliyagoda WSS

1,400

-

-

8

71

Improving of existing Kiriella WTP & Distribution Improvements

600

-

600

8

72

Augmentation of Kahawatte WTP and distribution expansion to Opanayake

4,500

4,500

4,800

73

 

Uva RSC

23,058

26,550

28,802

136

 

Badulla District

3,308

6,850

10,603

96

73

Improvements to Nayabedda water source and distribution improvement in Bandarawela and suburb area

 

1,000

4,055

42

74

Water Treatment Improvement in Badulla District WSS

3,268

1,350

1,333

 

75

Improvemnts to Kandekatiya wss

40

4,500

5,215

54

 

Monaragala District

19,750

19,700

18,199

40

76

Improvement to Icepihilla WTP, Wellawaya WSS

2,000

2,000

2,319

 

77

Wellawaya Stage II phase I

9,250

10,000

6,955

20

78

Water Treatment Improvement in Monaragala District WSS(Medagama, Siyabalanduwa, Sewanagala)

3,400

200

232

1

79

Capacity and Distribution improvement to Buttala WSS

4,300

1,500

1,738

19

80

Bibila Medagama WSS -Phase l

800

6,000

6,955

1

 

East RSC

30,600

15,850

22,594

269

 

Ampara District

20,900

1,750

7,050

86

81

Improvement of Service Level at Panama WSS

 

450

1,250

1

82

Improvement to Thirukkovil WSS

6,500

-

4,725

14

83

Improvement of Dehiytakandiya & Lihiniyagama WSS

4,700

600

550

54

84

Improvement of Bangalawadiya WTP at Sammanthurai

9,000

-

-

 

85

Improvement of Padiyathalawa WSS

700

700

525

17

 

Batticaloa District

 

5,000

805

48

86

Increase service coverage   in Unnichchai and surrounding areas

   

805

28

87

Augmentation of Valachchanai Paper Mill WSS

 

5,000

0

20

 

Trincomalee District

9,700

9,100

14,739

136

88

Distribution improvement in Kinniya DS area

   

2,025

4

89

Upgrading Muthur WTP & Intake improvement at Neelapola

8,500

8,500

2,230

 

90

Service level improvement to Trincomalee City and Surrounding areas

   

3,525

15

91

Increasing service coverage and Service level improvement in Dehiwatha , Thoppur and surrounding areas

   

1,210

91

92

Water quality improvement in Pulmoddai WSS

1,200

600

1,910

 

93

Water Source improvement in Eachchliampattu WSS

   

804

8

94

Water supply extension to Naddouththu and Sorrounding areas from Muthu WTP

   

3,035

17

95

Intake Improvement of Integrated Trincomalee WSS at Allai Kanthale

     

1

 

TOTAL

 

295,767

238,472

1,405

 

Project Name

Length of Pipe Laying(km)

Total New Connections (Nos.)

Distribution Infilling & Expansion

4,656

243,454

 

Western Central RSC

118

13,450

 

Colombo District

118

13,450

1

Laying of Pipes Along Infilling Areas of Towns East of Colombo District Water Supply Project -Phase I

28

4,000

2

Laying of Pipes Along Infilling Areas of Towns East of Colombo District Water Supply Project -Phase II

90

9,450

 

Western North RSC

635

33,500

 

Gampaha District

635

33,500

3

Supply & laying of pipes from Delgoda to Belummahara

10

2,000

4

Kelaniya Distribution Improvement - Phase I (Water Supply to Parakandeniya Area in Gampaha District

18

1,500

5

Implementation of infilling work in ongoing Katana Water Supply Project Area - Stage I

21

1,500

6

Kelaniya Distribution Improvement - Phase II

10

1,500

7

Implementation of balance part of distribution network in ongoing Gampaha Attanagalla and Minuwangoda Integrated Water Supply Scheme - Gampaha and Nittambuwa area

220

10,000

8

Implementation of infilling work in ongoing Katana Water Supply Project Area - Stage II

21

1,500

9

Distribution Improvement  in Gampaha - Stage I.

20

1,500

10

Infilling work in Katana Water Supply Project Area - Stage III

195

5,500

11

Infilling Work of Gampaha, Attanagalla and Minuwangoda Integrated Water Supply Scheme

120

8,500

 

Western South RSC

225

11,000

 

Kalutara District

225

11,000

12

Distribution expansion of Matugama / Agalawatta areas in Kalutara district

225

11,000

 

North Western RSC

1,247

43,985

 

Kurunegala District

747

22,070

13

Distribution Expansion in Deduru Oya Integrated Water Supply Project & Ambanpola, Galgamuwa Area

205

9,200

14

Distribution Expansion in Polgahawela - Pothuhera - Alawwa Integrated Water Supply Project

542

12,870

 

Puttalam District

500

13,500

15

Distribution Expansion in Anamaduwa Integrated Water Supply Project

500

13,500

 

North Central RSC

199

8,466

 

Anuradhapura District

189

8,396

16

Distribution infilling and extension  of Habarana WSS

47

1,554

17

Distribution infilling and extension of Madatugama WSS

142

6,842

 

Polonnaruwa District

9

70

18

Distribution infilling of Hingurakgoda WSS

3

25

19

Distribution  infilling of Minneriya WSS

2

15

20

Distribution  infilling of Polonnaruwa & Gallela WSS

5

30

 

North RSC

184

4,575

 

Jaffna District

68

1,725

21

Infilling of Distribution lines in Jaffna Region (Jaffna, Kilinochchi, Mullaithivu)

68

1,725

 

Mullaitivu District

30

500

22

Infilling and Distribution Expansion of WaSSIP (Kilinochchi/Mullaithivu) in Kilinochchi & Mullaithivu

30

500

 

Vavuniya District

86

2,350

23

Infilling of Distribution lines in Vavuniya Region (Mannar WSS, Adampan WSS, Thevanpiddy WSS, Vidathalthevu WSS and vavuniya WSS-2 Stages )

86

2,350

 

Central RSC

272

24,179

 

Kandy District

191

22,200

24

Distribution & Transmission of Marassana WSP

30

1,200

25

Connection enhancement programe in Central province

161

21,000

 

NuwaraEliya District

20

1,079

26

Proposed pipeline extension in Ginigathhena, Walapane and Maskeliya WSSs

20

1,079

 

Matale District

61

900

27

Distribution Improvement  of Wilgamuwa WSP

10

400

28

Distribution & Transmission of Laggala WSP

51

500

 

Southern RSC

862

52,500

 

Matara District

862

52,500

29

Matara Stage IV Distribution Improvement Project - Phase I

862

52,500

 

Sabaragamuwa RSC

64

18,300

 

Rathnapura District

51

14,300

30

Godakawela Distribution expansion

15

1,300

31

Improvement and taking over  of CBOs in Padalangala and Thorakolayaya area

36

13,000

 

Kegalle District

13

4,000

32

Distribution improvements in Ruwanwella WSS

13

4,000

 

Uva RSC

201

16,294

 

Badulla District

153

11,171

33

Transmission and Distribution Expansion of Ettampitiya water supply project

7

1,635

34

Taking over bulk water supply connection to NWSDB by doing improvement in Badulla District

10

3,161

35

Distribution improvements in Demodara WSS

136

6,375

 

Monaragala District

48

5,123

36

Transmission and Distribution Expansion of Siyabalanduwa  WSS

16

1,090

37

Taking over of Bulk Water Supply connection to NWSDB by doing improvements in Monaragala District

10

3,161

38

Taking over of Sooriyaara ( Wassip) WSS and extension to Nikawewa balance  and Mahawewa  area

23

872

 

East RSC

649

17,205

 

Ampara District

532

14,355

39

Extension to Serankade Village at Padiyathalawa

62

1,850

40

Infilling at Aranthalawa, Tempitiya, Borapola and Pullumalai villages in Mahaoya

51

1,375

41

Infilling at Centralcamp, Gonagalla, Paragahakele & Uhana WSS

296

8,400

42

Pipeline extension and infilling to Damana, Panankadu, Alikambe-Kannagikiramam & Akkaraipattu WSS

124

2,730

 

Batticaloa District

90

2,525

43

Distribution Expansion in Batticaloa District

90

2,525

 

Trincomalee District

27

325

44

Water Supply extension to Sooroyapura in Kanthale DS Division

27

325

 

TOTAL

4,634

235,039

Business Efficiency Improving Projects (NRW Reduction & Energy Saving )

1,553

16,693

 

Western South RSC

19

7,664

 

Kalutara District

19

7,664

45

Laying of Transmission main from Alwis Place to Wadduwa

12

3,272

46

Laying of 500mm dia. DI pipe line from Kethhena WTP to Central Junction

7

4,392

 

North Western RSC

   
 

Kurunegala District

   

47

Lake Side Pump Installation (Energy Project)

   
 

North Central RSC

32

509

 

Anuradhapura District

3

 

48

Anuradhapura New Town WSS-Replacing of pumping lines of Stage II & III water towers

3

 

49

Supply and installation of horizontal split casing pumps at Nuwarawewa WTP for Stage II & III water tower

   

50

Supply & installation of Surge Vessel to Anuradhapura North WSS

   
 

Polonnaruwa District

29

509

51

Replacing of  Gravity main from Minneriya (Patapilikanda Sump) to Hingurakgoda Tower

6

 

52

Distribution line replacement of Aralaganwila WSS

17

436

53

Distribution line replacement of Manampitiya WSS

7

73

54

Supply and installation of surge vessel at Minneriya WTP for transmission line to Patapilikanda sump

   
 

North RSC

35

3,600

 

Jaffna District

35

3,600

55

NRW Reduction Programmes in (Jaffna, Kilinochhci, Mullaithivu, Vavuniya & Mannar)

35

3,600

56

Solar Power System  for Jaffna & Vavuniya Regions

   
 

Sabaragamuwa RSC

   
 

Rathnapura District

   

57

Capacitor bank-Muwagama Intake, Emblipitiya TP, Embilipitiya Intake, Kahawaththa Intake & Balangoda hospital Intake

   

58

Intake Pump-Balangoda Old plant

   

59

Intake Pump-Muwagama plant

   

60

High lift Pump-Muwagamkanda to Samagipura plant

   

61

High lift Pump- Samagipura tank to Konagoda tank

   

62

Solar Power (PV) system for Ratnapura Region

   

63

Intake Pump-Kahawaththa

   
 

Kegalle District

   

64

Solar Power (PV) system for Kegalle Region

   
 

East RSC

1,467

4,920

 

Ampara District

1,449

2,695

65

Replacement of PVC pipe service connection to HDPE pipe in Ampara & Akkaraipattu region

1,217

1,345

66

Zoning arrangement at water supply schemes in Ampara & Akkaraipattu Region

55

675

67

Replacement of Old Standard pipe (unusual diamater pipe) in the distribution system in Akkaraipattu Region

177

675

 

Batticaloa District

   

68

Connection Transfer  to PE and shifting meters to suitable locations in Batticaloa region

   
 

Trincomalee District

18

2,225

69

Connection Transfer  to PE and shifting meters to suitable locations  in Trincomalee   Region

 

2,025

70

Replacement of bundle pipe in the distribution system in Trincomalee Region

17

100

71

Zoning arrangement  in distribution system -Trincomalee  Region

1

100

Priority for enhancement of Revenue by Providing Connections for revenue Generating Consumer Segment

79

        1,637

 

North Western RSC

47

1,450

 

Kurunegala District

47

1,450

72

Distribution expansion in Kurunegala WSP

9

400

73

Distribution Expansion in Thorayaya WSP

38

1,050

 

North Central RSC

6

2

 

Polonnaruwa District

6

2

74

Water Supply to Aralaganwila Police Training School - Aralaganwila WSS

6

2

 

East RSC

26

185

 

Batticaloa District

26

185

75

Water Supply extension to tourist areas at Passikuda in  Batticaloa District

6

25

76

Extension of pipe laying in tourist area Kallady, Batticaloa District

20

160

 

TOTAL

6,288

261,784

 

S#

Name of the Project

District

WTP Capacity (m3/d)

Length of Pipe Laying (km)

Total New Connections (Nos.)

Batch 1: New Projects to be implemented in year 2021 with Water treatment Plant and Intake Construction

 

Western Central RSC

 

5,000

-

-

1

Construction of New WTP at Awissawella

Colombo

5,000

   
 

Western North RSC

 

40,000

1,631

42,500

2

Mirigama WSP - Stage I

Gampaha

20,000

778

20,750

3

Divulapitiya WSP - Stage I

Gampaha

20,000

853

21,750

 

North Western RSC

 

154,000

3,271

248,020

4

Katupotha - Bamunakotuwa - Panduwasnuwara WSP

Kurunegala

20,000

722

31,700

5

Bingirya - Udubaddawa & Makadura-Pannala- Kuliyapitiya Integrated WSP  - Phase I

Kurunegala

40,000

1,133

63,400

6

Dankotuwa WSP - Phase I

Puttlam

20,000

234

31,700

7

Towns North Of Kurunegala (TNK) WSP - Phase 1

Kurunegala

50,000

254

78,000

8

Chilaw WSP - Stage II

Puttlam

12,000

395

20,160

9

Puttalam WSP- Stage II

Puttlam

12,000

533

20,160

 

North RSC

 

50,000

-

36,000

10

Jaffna Kilinochchi IWSP - Stage II

Kilinochchi

50,000

 

36,000

 

Central RSC

 

74,500

1,006

133,840

11

Kundasale Haragama WSP

Kandy

50,000

357

91,300

12

Nanuoya WSP

Nuwara Eliya

2,000

72

4,525

13

Hapugasthalawa WSP

Nuwara Eliya

7,500

135

10,313

14

Delthota WSP

Kandy

5,000

122

6,930

15

Medadumbara Panwila WSP

Kandy

10,000

321

20,735

 

Southern RSC

 

105,000

935

102,300

16

Greater Galle WSP - Stage III

Galle

50,000

387

54,300

17

Baddegama IWSP-Stage I

Galle

30,000

217

28,000

18

Lunugamwera IWSP - Phase I &  II

Hambanthota

25,000

331

20,000

 

Sabaragamuwa RSC

 

55,500

393

56,403

19

Kiriella WSP

Rathnapura

3,000

34

4,740

20

Embilipitiya Paper Mill WSP

Rathnapura

30,000

 

20,325

21

 Balangoda WSP - Stage II 

Rathnapura

7,500

258

10,363

22

Eheliyagoda WSP

Rathnapura

15,000

102

20,725

 

Uva RSC

 

50,000

1,271

54,092

23

 Bandarawela WSP -  Phase I &II

Badulla

20,000

651

23,183

24

Badalkumbura WSP

Monaragala

5,000

77

5,215

25

Bibila Medagama WSP - Phase ll

Monaragala

5,000

149

6,955

26

Hambegamuwa WSP

Monaragala

4,000

138

4,057

27

 Loggaloya WSP

Badulla

4,000

102

3,091

28

 Wellawaya WSP - Stage II phase Il

Monaragala

12,000

156

11,591

 

East RSC

 

39,000

384

54,225

29

Morawewa & Gomarankadawala WSP

Trincomalee

4,000

303

5,100

30

Greater Trincomalee Expansion WSP

Trincomalee

20,000

30

25,500

31

Valachchenai WSP

Batticaloa

15,000

51

21,125

 

Sub Total 1

 

573,000

8,891

725,280

Batch 1: New Projects to be implemented in 2021 with  Pipe Laying and Other Works

 

Western Central RSC

 

-

351

-

32

Upgarading Water Supply Facilities in Jubilee Kotte Area

Colombo

 

133

-

33

Upgarading Water Supply Facilities in Kolonnawa Area

Colombo

 

219

-

 

Western North RSC

   

497

77,000

34

Infilling work of KRB Project Stage II in Kelaniya Region

Gampaha

 

497

77,000

 

Western South RSC

 

-

296

26,000

35

Ingiriya - Hadapangoda WSP

Kaluthara

 

296

26,000

36

Construction of Salinity Barrier - Kalu Gaga

Kaluthara

   

-

 

North Western RSC

 

-

248

7,950

37

Melsiripura WSP

Kurunegala

 

123

3,975

38

Extension to Rasnayakapura

Puttlam

 

125

3,975

 

North RSC

 

-

38

850

39

Chunnakam WSP

Jaffna

 

38

850

 

Central RSC

 

-

758

51,304

40

 Greater Matale WSP - Stage II

Mathale

 

758

51,304

 

Sub Total 2

 

-

2,188

163,104

 

TOTAL- Batch 1

 

573,000

11,079

888,386

Batch 2: New Projects to be implemented in year 2022-2023 with Water treatment Plant and Intake Construction

 

Western Central RSC

 

180,000

 

-

41

Weliwita WSP - Head Works (Stage-1)

Colombo

180,000

 

-

 

Western North RSC

 

57,000

969

69,400

42

Kiridiwela WSP – Stage I

Gampaha

30,000

419

40,000

43

Gampaha Attanagalla Minuwangoda WSP - Stage II

Gampaha

27,000

550

29,400

 

Western South RSC

 

50,000

600

80,000

44

Kethhena Improvement & Expansion Project

Kaluthara

50,000

600

80,000

 

North Western RSC

 

22,000

-

34,760

45

Kalpitiya WSP

Puttlam

12,000

 

18,860

46

Galgamuwa - Ehatuwewa - Ambanpola WSP

Kurunegala

10,000

 

15,900

 

North Central RSC

 

64,000

3,474

99,284

47

Anuradhapura South WSP - Phase II

Anuradhapura

10,000

257

12,856

48

Palugaswewa WSP

Anuradhapura

5,000

355

6,428

49

Towns East of Polonnaruwa WSP

Polonnaruwa

48,000

2,862

80,000

 

North RSC

 

2,750

74

2,600

50

 Kankesanthurai WSS- Stage 1

Jaffna

1,000

21

850

51

 Chulipurm WSS-Stage 1

Jaffna

750

48

1,250

52

 Point Pedro & VVT (RO Plant) WSS

Jaffna

1,000

5

500

 

Central RSC

 

48,500

910

60,616

53

 Hasalaka WSP

Kandy

7,500

208

13,200

54

 Pundaluoya WSP 

NuwaraEliya

5,000

72

6,880

55

Hatharaliyadda WSP

Kandy

5,000

111

6,963

56

Nawalapitiya Pallegama WSP

Kandy

2,000

58

2,750

57

 Pupuressa Atabage WSP 

Kandy

10,000

148

12,430

58

Ganga Ihala Korale WSP 

Kandy

10,000

150

10,450

59

Naula Wahakotte WSP

Mathale

4,000

80

5,193

60

Kothmale River Side WSP

Kandy

5,000

83

2,750

 

Southern RSC

 

98,000

521

98,300

61

 Imaduwa WSP

Galle

6,000

64

7,300

62

 Kataragama Long term -Phase I &II

Hambanthota

15,000

106

5,600

63

Ruhunupura - Stage II

Hambanthota

20,000

42

10,000

64

Augmentation of Hakmnana WSS

Mathara

7,500

11

9,000

65

 Deniyaya WSP

Mathara

6,000

156

7,400

66

 Morawaka WSP

Mathara

6,000

142

8,500

67

 Mathara - Stage V

Mathara

30,000

 

42,500

68

 Deyyandara-Mulatiyana WSP

Mathara

7,500

0

8,000

 

Sabaragamuwa RSC

 

82,000

317

119,030

69

 Doloswala, Nivithigala, Karavita WSP

Rathnapura

5,000

0

6,855

70

 Dehiowita WSP

Rathnapura

15,000

0

23,600

71

Kuruvita WSP

Rathnapura

5,000

18

6,975

72

Kalawana WSP

Rathnapura

5,000

106

5,380

73

Warakapola WSP

Kegalle

15,000

193

15,800

74

Integration of Kegalle WSS

Kegalle

10,000

0

20,200

75

Rambukkana WSP

Kegalle

15,000

0

24,600

76

 Greater Rathnapura WSP - Stage II

Rathnapura

18,000

 

17,500

 

Uva RSC

 

73,500

6,277

81,506

77

Gawarammana Bogahakumbura WSP

Badulla

15,000

173

16,227

78

 Yahalarawa WSP

Badulla

2,000

48

2,319

79

 Ulhitiya WSP

Badulla

4,000

136

3,477

80

 Thaldena Meegahakiula WSP

Badulla

5,000

68

4,057

81

 Welimada Stage II

Badulla

4,000

101

2,319

82

 Thanamalvila Sevanagala IWSP

Monaragala

10,000

5,750

1,932

83

 Springvelly WSP

Badulla

2,000

 

2,750

84

 Haldummulla WSP

Badulla

1,500

 

1,738

85

 Greater Monaragala WSP

Monaragala

30,000

 

49,050

 

East RSC

 

18,500

205

17,675

86

Water supply Improvements in   Muthur  East  area

Trincomalee

10,000

52

12,750

87

Lahugala WSP

Ampara

1,000

 

1,310

88

Dehiyaththakandiya WSP

Ampara

7,500

153

2,415

 

Sub Total 1

 

696,250

13,346

663,171