Water Quality
Best Laboratory of the NWSDB – Awarded on World Water Day 2019
|
ISO /IEC 17025 Laboratory Accreditation for Chemical & Biological Testing
|
|
|
Energy Efficiency Improvement Activities
Western south carried out many projects to improve energy efficiency activates. Through those kinds of projects, they can achieve substantial progress and activities upgraded to a higher level qualitatively and quantitatively. Saving energy through energy efficiency improvement projects can cost less. And also it helps to achieve sustainability goals including multiple economic and environmental benefits. Energy savings can reduce operating costs for local governments, freeing up resources for additional investments in energy efficiency and other priorities. Energy efficiency can also help reduce air pollution and GHG emissions, improve energy security and independence, and create jobs.
1.Replaced Pumps at Maggona
Under the energy efficiency improvement program at the NWSDB, M&E Division carried out the energy audit with the assistance of the Western south O&M team to identify the operating parameters and efficiency of the Maggona pumps. Two Numbers pumps (1 duty & 1 Standby) are used to pump the water (15hrs/day) to the water tower (for Approx. 4000 connections) using VFD in the control panel. As a result of energy audit, we could calculate the efficiency of the pumps and SEC values. The efficiencies of the pumps were around 59% and SECs were between 0.17-0.18kwh/m3. These pumps were replaced by new pumps which efficiency is above 70% on 2015. The current SEC is around 0.9 kwh/m3.The above energy project maximum payback period is 4 years and 6 months and the investment cost is 12.5 Million.
2.Replaced Pumps at Beruwela
The energy improvement project was carried out under the guidance of Energy improvement program for Beruwela Pump House. Through Energy audit, we found the efficiency of the pumps are around 60% and SECs were between 0.09-0.1 kwh/m3. The new pumps with high efficiency were replaced. Then, the efficiency of the pumps can be increased above 75% at the end of 2017. The investment cost of this project is 20 Million and maximum payback period is 4 year and 4 month.
3. Pilot project of 30kw solar powered net metering system in western South RSC office
NWSDB annually spends Rs. 3.3 billion for its electricity mainly for central air condition and building facilities. NWSDB is the largest customer for Ceylon Electricity Board. As one of the steps of energy efficiency program, solar energy project was carried out in the Regional Support Centre (Western South).Regional Support Centre (Western South) is located at Angulana station road in Moratuwa near to the Head office of NWS&DB. It is four stories building including Auditorium in fourth floor and total floor area is 2120 m2 with two separate car parks roof area are 220 m2 and 98 m2. About 90 of employees work in the office building. Average power consumption per month is 11,000 kWh. To reduce the Power Consumption of the RSC (Western-South) the proposed capacity of the solar project is 30 kW. By that, the average unit of 3600 kW per month added to national grid. Through this project, the saving energy cost per month is around 75,000.00 LKR. The investment project cost is 4.35 Million. The maximum payback period is 4 year and 5 months.
4. Solar Power Projects
There are few solar projects in western south RSC.
a) 20kw solar powered net metering system at Bandaragama Area Regional Manager Office.
Area Engineer Office (Bandaragama) is located at Janadipathi Mawatha in Bandaragama. It is three stories building with roof area is 270 m2 and total floor area is 603 m2. About 75 no of employees work in the office building. Average power consumption per month is 1,400 kWh. The capacity of 20kw of solar project was carried out under the energy efficiency program. Through this project, the unit of 2200 kwh per month can be added to the national grid. The investment cost is 2.5 Million and payback period is 4 year and 4 months. The monthly saving is around Rs.48,000.00.
b)30 kw solar powered net metering system at Dehiwela Regional Manager Office.
Regional Manager Office (Dehiwala) is located at Atapattu Place in Dehiwala near to the Dehiwala Zoo. It is three stories building including conference hall in third floor and total floor area is 824 m2 with one separate car park roof area is 115 m2. About 63 no of employees work in the office building. Average power consumption per month is 5,900 kWh. The energy efficiency program proposed to install solar project with the capacity of 30kw. The investment of this project is Rs. 4 million. Through this solar project, the unit of 3000 kWh is added to national grid per month. The energy saving cost is around Rs. 65,000.00 and also the maximum payback period is 5 year.
c)20 kw solar powered net metering system at Kaluthara Regional Manager Office.
Regional Manager Office (Kalutara) is located at No.15, Cooray Road, in Kalutara., near to the Kalutara Town. It is two stories building with roof area is 230 m2 and total floor area is 460 m2. About 60 no of employees work in the office building. Average power consumption per month is 4,750 kWh. Under the guidance of energy efficiency program, the solar project with the capacity of 20kw was installed. By that, the unit of 2200 kwh per month is added to national grid. Due to this energy saving, the energy saving cost is around Rs. 48,000.00. The investment cost for this project is Rs. 3 million. The maximum payback period is 5 year and 2 months.
d) 30 kw solar powered net metering system at Panadura Regional Manager Office.
Regional Manager Office (P/H) is located at 44, Divisional Office, Weeraman Road in Panadura near to the Panadura Town. It is three stories building with roof area is 270 m2 and total floor area is 603 m2. About 50 no of employees work in the office building. Average power consumption per month is 3,900 kWh.The capacity of 30kw of solar project was carried out under the energy efficiency program. Through this project, the unit of 3600 kWh per month can be added to the national grid. The investment cost is 4.5 Million and payback period is 4 year and 8 months. The monthly saving is around Rs.78, 000.00.
5. Pumps Automation at Moratuwa High lift pump house
The water pumped using three pumps from Moratuwa reservoir into Kadolana Tower. Due to these pumps, the energy is high for the pumps. The energy efficiency program proposed the pump arrangement. In which water is distributed through tower during off-peak time. And also water is directly distributed from Moratuwa reservoir to people during peak time without flowing through tower. At this time, the required powers for the pumps are less due to less head.
Write comment (0 Comments)
Sociology Activities, Public Relation & Welfare Activities
Development Activities
Most of the Development Activities of the region are carried out by the Construction Section of the region .
CONSTRUCTION SECTION ( RSC WS )
Objective of Construction Section
Construction section is responsible for all the activities in relation to construction works and contract administration. The Construction Section plays a major role in the Regional Support Centre, which covers the three Operation & Maintenance (O&M) regions named Dehiwala, Panadura- Horana and Kalutara.
Key Functions of the section
Responsible for the major construction work within the RSC limits.
After the award of contracts, arrange the pre –construction meeting and give the kick-start for the work undertaken by the Contractor.
Carry out the construction activities as per the contract. |
Liaison with Road Authorities and other Institutions. |
Supervise the works to ensure that they are carried out in accordance with the specifications and other related conditions. |
Facilitate the contractor to carry out the works and coordinate all the stake holders involved in the works. |
Check the contractors’ monthly payment applications and certify them for the payments (as per the checklist). |
Valuation of variations and obtaining necessary VO committee approval for the payments accordingly. |
Give site instructions to the Contractor according the changes arises time to time. Take over the completed works. |
Issue taking over certificate, substantial completion certificate and completion certificate. |
Check the final bill and certify the payment as per the contract condition. |
Prepare duly signed fixed asset Forms & handover to Finance Division |
Check and certify “As built drawings”. |
Reconciliation of the materials and update.
|
ONGOING & RECENTLY COMPLETED DEVELOPMENT ACTIVITIES - 2021 First QTR |
|||||||||||||||||
Item No. |
Project |
Contract No. |
Contractor |
Contract Amount (Mn) |
Expected Completion date |
Paid up to 31.12.2018 |
Paid in 2019 |
Bills in Hand at |
Balance Fund req'd in 2019 (Mn) |
Approved Allocation for 2019 in Rev-3 (Mn) |
Physical Progress as at March 2021 |
Remarks |
|||||
Finance |
Const. Div. |
||||||||||||||||
REHABILITATION PROJECTS |
|||||||||||||||||
1 |
Excavation, Laying & Backfilling of 225mm, 160mm, 90mm dia. UPVC pipes & other works along Horana - Ingiriya road Wagawatta to Ingiriya at Horana WSS in Panadura - Horana Region |
2017/25 |
M/s. Brians Engineering (Pvt) Ltd |
25.45 |
Completed in 2020 |
7.77 |
7.79 |
6.19 |
3.00 |
9.19 |
6.00 |
100.0% |
83.0% |
Final Payment Certifcate to be prepared after the construction of AV chamber at Ingiriya Town |
|||
2 |
Excavation, Laying & Backfilling of 160mm, 90mm dia & 63mm dia. uPVC pipes & other works along Horana - Padukka Road near Owitiyagala Road Junction to Kananwila Pradeshiya Sabha at Horana WSS in Panadura- Horana Region |
2017/57 |
M/s. Brians Engineering (Pvt) Ltd |
6.63 |
Completed in 2019 |
1.33 |
1.87 |
2.56 |
1.00 |
2.56 |
5.20 |
100.0% |
87.0% |
Final Payment Certifcate to be prepared after the interconnection through culvert |
|||
3 |
Laying of DI Pipes, Fittings , Specials and Valves for Culvert Crossing & Bridge Crossings along Ingiriya- Meepe Road |
2017/85 |
M/s. Ravindu Engineeing & Construction |
2.59 |
Completed in 2020 |
0.00 |
0.00 |
0.00 |
0.00 |
0.30 |
0.60 |
100.0% |
0.0% |
Slow progress due to rain |
|||
4 |
Construction of Drive Through Building and Meter Readers' room for Area Engineer (Moratuwa) office |
2018/43 |
M/s. Karawgoda Construction |
6.82 |
Completed in 2020 |
1.37 |
1.89 |
0.00 |
0.00 |
1.50 |
7.50 |
100.0% |
37.0% |
||||
5 |
Supply & Placing of Filter Media for slow sand fillter at Mathugama |
2018/34 |
M/s. R.A.Building Materiel Suppliers |
3.79 |
1st Filter Completed in 2020 |
0.69 |
0.00 |
0.00 |
0.00 |
0.80 |
0.50 |
50.0% |
0.0% |
||||
6 |
Construction of Soysapura Pump House at Dehiwala/Moratuwa Region |
2018/95 |
M/s. Solanma Engineering (Pvt) Ltd |
12.80 |
Completed in 2020 |
0.00 |
4.85 |
2.20 |
0.00 |
3.70 |
8.20 |
100.0% |
64.0% |
||||
7 |
Laying of uPVC and DI pipes, Specials, DI valves and accessories for Raigampura Green Industrial and Techno Development Zone (Stage III) |
M/s. Dumindu Constructions & Company |
16.17 |
Completed in 2021 |
100.0% |
||||||||||||
8 |
Bid for Construction of 1st Floor of OIC Office at Piliminawatta for Mathugama/Piliminawatta/Bombuwala Water Supply Scheme |
M/s. Athukorala Construction |
6.90 |
Completed in 2021 |
100.0% |
||||||||||||
NRW PROJECTS |
|||||||||||||||||
9 |
Renovation of Beruwala Reservoir (Building & Civil Works) |
2018/59 |
M/s. Finex Engineering (Pvt) Ltd |
29.40 |
Completed |
0.00 |
11.10 |
0.00 |
3.00 |
3.00 |
14.00 |
100.0% |
|||||
10 |
Renovation of Maggona Tower |
2017/86 |
M/s. Finco Engineering |
9.98 |
Completed |
3.75 |
1.57 |
0.00 |
0.60 |
0.60 |
2.57 |
100.0% |
|||||
11 |
Tender for Renovation of Ground Reservoir at Alwis Place in Kalutara |
M/s. Finex Engineering (Pvt) Ltd |
74.19 |
Feb-21 |
60.0% |
||||||||||||
UTILITY SHIFTING PROJECTS |
|||||||||||||||||
12 |
Laying of uPVC, PE and DI pipes, specials, DI Valves and Accessories for Kawdana Attidiya Road |
2017/ 99R-02 |
M/s. Ceyoka Enginnering (Pvt)Ltd |
5.00 |
Completed in 2020 |
0.00 |
2.85 |
0.61 |
0.00 |
0.61 |
5.00 |
100.0% |
57.0% |
||||
13 |
Laying of 160mm uPVC & DI Pipes special , valves and Construction of Chambers of proposed pipe line (5.2km) for Wadduwa Moronthuduwa Road under NWSDB funds - Stage-I |
2018/40 |
M/s. MAGA Engineering |
7.12 |
Completed in 2020 |
0.00 |
3.96 |
0.00 |
1.63 |
2.00 |
17.60 |
100.0% |
56.0% |
IPC-3 (Rs. 1.63 Million) prepared |
|||
14 |
Laying of 160mm Upvc &DI Pipes special ,valves and Construction of Chambers of proposed pipe line (5.2km) for Wadduwa Moronthuduwa Road under NWSDB funds - Stage II |
2018/41 |
M/s. MAGA Engineering |
7.46 |
Completed in 2020 |
0.00 |
2.11 |
0.00 |
0.00 |
1.50 |
100.0% |
31.0% |
|||||
15 |
Laying of DI/ uPVC Pipes for Hill Street towards Nadimala Junction up to Bellantota Junction under Dehiwala Region |
2016/122 |
M/s. SD &CC |
71.54 |
Completed in 2019 |
12.57 |
0.00 |
0.00 |
(1.54) |
(1.54) |
0.00 |
100.0% |
114.0% |
Final Bill to be Prepared |
|||
RECHARGEABLE FUNDED PROJECTS |
|||||||||||||||||
16 |
Laying of 225mm dia.uPVC and DI pipes, Specials & Valves for Millaniya Industrial Zone - Stage I |
2017/89 |
M/s. C&C Engineering (Pvt) Ltd |
37.47 |
Completed in 2020 |
10.74 |
6.54 |
0.00 |
1.00 |
1.00 |
99.0% |
100.0% |
Flushing & Disinfection, Marker Posts to be completed |
||||
17 |
Supply & Laying of water transmission main at Wagawatta Industrial Zone |
2016/10/02.004 |
M/s. SAW Engineering (Pvt) ltd |
52.89 |
Completed in 2019 |
41.43 |
0.00 |
100.0% |
100.0% |
Only the Supervision is done by NWSDB |
|||||||
18 |
Laying of uPVC and DI pipes, Specials, DI valves and accessories for Water Supply to CGR Quarters Ratmalana |
M/s. Lakshieka Construction |
24.95 |
Sep-21 |
7.0% |
||||||||||||
19 |
Laying of uPVC and DI pipes, Specials, DI valves and accessories for 225mm dia. uPVC pipeline for Anguruwattota road - Raigamapura Green Industrial and Techno Development Zone (Stage-1) |
2018/89 |
M/s. Brians Engineers (Pvt) ltd |
28.90 |
Apr-21 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.0% |
92.0% |
|||||
20 |
Laying of uPVC and DI pipes, Specials, DI valves and accessories for Raigampura Green Industrial and Techno Development Zone (Stage II) |
M/s. Brians Engineers (Pvt) ltd |
18.89 |
Apr-21 |
92.0% |
||||||||||||
GRANT/FUNDED BY OTHER INSTITUTIONS/PROJECT FUND |
|||||||||||||||||
21 |
Kesbewa- Pokunuwita Road pipe laying (Kahatuduwa Interchange to Pokunuwita Junction) |
RDA/SRCP/JCB/ADB/CP-02 |
M/s. MAGA Engineering |
RDA Awarded Contract |
Completed in 2020 |
0.00 |
100.0% |
100.0% |
Only the Supervision is done by NWSDB |
||||||||
22 |
Gonapola - Pokunuwita Road pipe laying |
M/s. MAGA Engineering |
RDA Awarded Contract |
Dec-21 |
25.0% |
||||||||||||
23 |
Rehabilitation & Improvements to Cross Junction to Digarolla Bridge |
RDA |
M/s. Solanma Engineering (Pvt) Ltd |
RDA Awarded Contract |
Completed in 2020 |
0.00 |
100.0% |
100.0% |
Only the Supervision is done by NWSDB |
||||||||
24 |
Construction of Pipeline Installation and Leak DetectionTraining Yard |
JICA |
USD 43,580.20 plus Rs.33,57 Mn |
Completed in 2020 |
100.0% |
||||||||||||
25 |
Construction of OIC Office for Horana OIC |
AMAIWSP |
AMAIWS Project Funded |
Mar-21 |
25% |
||||||||||||
26 |
Tender for Construction of 500m3 Capacity Ground Reservoir and Pump House for Dahampahangama Water Supply Scheme |
M/s Kandy Construction |
AMAIWS Project Funded (32.95 Mn) |
May-21 |
60% |
||||||||||||
27 |
Renovation of Regional Manager Office, Kalutara |
Southern Construction |
AMAIWS Project Funded (7.60 Mn) |
May-21 |
25% |
||||||||||||
Write comment (0 Comments)
Rural Water Supply Activities
Panadura/Horana Region
1. Panadura Water Supply Scheme -
Water Safety Plan report revision-3 is completed and the Water Safety Plan is implemented in operation level.
2. Ingiriya/Nimalagama Water Supply Schemes -
Water Safety Plan report revision-2 is completed and the Water Safety Plan is implemented in operation level.
3. Bandaragama Water Supply Scheme -
Water Safety Plan report is completed up to module-8 and the Water Safety Plan is implemented in operation level.
4. Horana Water Supply Scheme -
Water Safety Plan report is completed up to module-6 and the Water Safety Plan is implemented in operation level
Kalutara Region
1. Aluthgama/Beruwala/Payagala Water Supply Schemes -
Water Safety Plan report revision-3 is completed and the Water Safety Plan is implemented in operation level.
2. Mathugama Water Supply Scheme -
Water Safety Plan report revision-2 is completed and the Water Safety Plan is implemented in operation level.
3. Bombuwala/Pilaminawatta Water Supply Schemes -
Water Safety Plan report revision-2 is completed and the Water Safety Plan is implemented in operation level.
4. Kalutara/Wadduwa/Waskaduwa Water Supply Schemes -
Water Safety Plan report is completed up to module-7 and the Water Safety Plan is implemented in operation level.
Dehiwala/Moratuwa Region
1. Moratuwa Water Supply Scheme -
Water Safety Plan report revision-1 is completed and the Water Safety Plan is implemented in operation level.
2. Dehiwala Water Supply Scheme -
Water Safety Plan report revision-1 is completed and the Water Safety Plan is implemented in operation level.
Write comment (0 Comments)
News & Events
Price Awarding Ceremony : Poster Competition - World Water Day 2021
Opening of Green Conference Room (06.04.2021)
Celebration of New Year - 2021
Celebration of New Year - 2020
Secret Santa - Christmas Celebration - 2018
![]() |
Social Services
Donation to a Student of Prince of Wales College
![]() |
Write comment (0 Comments)
NRW Reduction
NRW
What is the term of NRW?
Non-Revenue Water (NRW) = “Net Production” - “Revenue Water”
The difference between the volumes of water delivered in to a Network and billed authorized consumption
How can create a NRW?
Real Losses
- Distribution main Leaks (Visible/Invisible/Un reported)
- Transmission main Losses (Visible/Invisible/Un reported)
- Reservoirs Leakage & Over Flows.
Main Leak | Minor Leak |
![]() |
![]() |
Apparent Losses
- Production metering in accuracies
- Customer metering inaccuracies
- Unbilled authorized consumption
- Illegal Connections
- Administrative Errors
![]() |
![]() |
How to reduce the NRW?
- Reduction of Real losses and Apparent Losses.
- Mainly Repairing of any kind of Leaks with in the minimum time duration
- Using Good effective preventive maintenance programme.
- Water balancing work at DMA systems.
![]() |
![]() |
Transfer the NRW at Massages to Authorized officers
- If you see the any kind of Water Leaks Please Call 1939 using any phone. (this is a free of charge call)
![]() |
![]() |
![]() |
If you are living at Dehiwala, Moratuwa or Kalutara District, If can’t achieve 1939 Free Call Number,
Please Call Hot Line
Dehiwala |
011-2734444 |
Moratuwa |
011-2648899 |
Kaluthara |
034-2223079/034 - 2222278 |
Panadura-Horana |
038-2241856-7 |
RSC (W-S) |
011 - 2224888 |
Write comment (0 Comments)
Page 1 of 2