Project Name (Donor) District Type of Project No. of Beneficiaries Duration Total Estimated Cost (Rs. million) Actual Expenditure as at end 2010 (Rs. million) Physical Progress %
From To
Central Province
Water Sector Development Project 1 Sub Project 4 Greater Kandy WS Phase I Stage II (JICA) Kandy Augmentation 616,000 Oct 2007 Jul 2012 4,164.00 4,681.63 94
Greater Dambulla WS – Stage 1 (INDIA) Nuwara Eliya Augmentation   2012 Jul 2014 9,593.00 5,808.50 23
Eastern Province
Eastern Coastal Towns of Ampara District (ECTAD) WS Phase II (Australia) Ampara New 161,400 Oct 2002 Dec 2010 11,078.20 10,712.13 100
Eastern Province Water Supply Development Project (JICA) Ampara New   2010 2015 6,526.00 1,407.16 70
Integrated Water Supply Scheme for the Unserved Area of Ampara District Phase III (Australia) Ampara New 80,000 2007 2015 18,012.00 9,904.30 36
Northern Province
Jaffna Killinochchi Water Supply & Sanitation (ADB VI) Jaffna Augmentation 15,000 2011 2016 18,328.20 194.56 15
Killinochchi Rehabilitation Water Supply Project (JICA)     15,000 2013 2015 1,900.00  
Immediate Arragements to provide Water Supply to Kilinochchi (New 2 KR) (JICA )       2013 2015 260 150 65
North Central Province
Thambuttegama WS (China) Kurunegala New   2014 2017 1,805.00  
Anuradhapura North Intergrated Water Supply (JICA)       2013 2015 9,736.00  
Southern Province
Ruhunupura WS Development (Korea)       Jan 2011 Mar 2013 13,131.30 5,378.20 46
Kirama, Katuwana, Middeniya & Angunakolapelessa Integrated WS (China) Galle Augmentation 160,000 Jan 2012 Jan 2013 2,662.00  
Rehabilitation & Augmentation of Kirindioya Water Supply (Austria) Hambantota Augmentation 30,000 Feb 2007 Dec 2009 2,104.83 1,914.25 100
Uva Province
Badulla – Haliela and Ella Integated WS (US Exim Bank)       2013 2015 10,396.50 5.1  
Mahiyangana Water Supply (Austria)       2013 2016 1,785.00  
Western Province
Water Sector Development Project I
Towns North of Colombo WS -stage II (JICA)
Colombo Extension 200,000 2007 2014 6,490.00 5,750.36 97
Kelani Right Bank WTP (DANIDA) Colombo New 1,500,000 Oct 2008 Dec 2013 12,000.00 9,477.31 98
Rehabilitation & Augmentation of Labugama – Kalatuwawa WTP (Hangary) Colombo Rehabilitation 375,000 2013 2016 8,100.00 1.29
Augmentation of Negombo WS (DUTCH) Gampaha Augmentation 137,500 2008 2013 7,302.00 6,703.69 98
Water Sector Development Project I
Greater Colombo Water Rehabilitation (JICA)
Colombo Rehabilitation 100,000 2007 2015 4,785.00 3,476.78 74
Water Sector Development Project II (JICA)
Kaluganga Water Supply Project Phase I -Stage II & Non Revenue Water Reduction in Colombo City (NRW Master Plan)
      Jul 2008 Dec 2015 10,846.00 4,650.60 66
Consultancy Services for Non Revenue Water (NRW) Engineering Study, Master Plan Update and Institutional Development       Oct 2011 Jun 2013 412.1  
Energy Conservation Project at Ambatale WTP (GERMAN)       2012 2014 6,220.00  
Capacity Development Project for NRW reduction in Colombo City (JICA)       2010 2011 201 30.6 100
Colombo Water Supply Service Improvement Project (ADB)       2012 2018 28,800.00 8.12  
Katana WS (China)       2014 2015 1,641.00  
Water Treatment Facilities Moratuwa / Panadura, Ambatale and in Negombo (Spanish) [formerly Galagoda WSS] Colombo, Gampaha New 10,000 Oct 2007 Dec 2009 2,690.00 2,672.34 100
Sabaragamuwa Province
Greater Ratnapura Water Supply Project (Spain)       Jan 2012 Dec 2016 9,928.00  
Kolonna/ Balangoda Water Supply Project (Belgium)       2011 2015 4,658.00 1,244.50 5
North Western Province
Greater Kurunegala (China)       Jan 2013 Dec 2015 11,943.00  
Wandura Pinu Ella WS (China)       Jan 2012   9,756.00  
Inter Provincial Projects/ Programmes
Secondary Towns Rural Community Based WS & Sanitation (ADB 4th project) Polonnaruwa, Anuradhapura, Trincomalee, Hambantota, Batticaloa New 968,000 (Water) & 171,500 (Sanitation) Jan 2004 2013 29,680.00 25,692.94 95
Dry zone urban Water & Sanitation Project(ADB V)     86,000 Jun 2009 Jun 2014 13,029.60 1,494.19 31
Hambantota/ Ambalantota/ Weligama/ Kataragama Implementation Project & Badulla, Bandarawela Integrated Feasibility Studies (UNIHA) Hambantota, Matara Augmentation 150000 & SLI 200,000 Nov 2004 Dec 2013 2,126.00 1,767.88 98