Project Name District Type of Project No. of Beneficiaries Duration Total Estimated Cost (Rs. million) Actual Expenditure as at end 2010 (Rs. million) Physical Progress %
From To
Central Province
Matale WS Matale Augmentation 15,000 Jan 1999 Apr 2014 384.9 347.85 90
Kundasale Integrated WS – Stage II Kandy Augmentation 130,000 Jan 1998 Dec 2014 1,400.00 1,276.73 85
Marassana WS Kandy New 25,000 Jan 1996 Dec 2014 222 282.12 95
Thalawakele/ Lindula WS Nuwara Eliya Augmentation 15,000 Jan 2000 Dec 2014 172 188.69 90
Palapathwela WS Matale Extension 22,000 Jan 2000 Dec 2014 150 159.15 80
North Central Province
Hingurakkoda WS Polonnaruwa Augmentation 6,000 Jan 1996 Dec 2015 130 124.94 98
Minneriya WS – Stage II Polonnaruwa Augmentation 69,000 Jan 2007 Dec 2015 100 102.58 97
Medirigiriya WS – Stage I Polonnaruwa New 60,000 Jan 2007 Dec 2015 638 574.66 70
Mahanelubewa WS Anuradhapura New   Dec 2010 Dec 2014 129.7 113.74 97
Ippalogama Housing Scheme WS Anuradhapura Extension 18,000 Jan 2007 Dec 2014 798 598.12 92
Parasangaswewa Anuradhapura New 1,000 Jan 2013 Dec 2013 31.6  
Deyata Kirula       Jan 2011 Dec 2012 830 528.67 85
Eastern Province
Kantale WS Trincomalee Augmentation 25,000 Jan 1999 Dec 2012 274.8 216.37 69
Tampalakamam WS Trincomalee Augmentation 30,000 Jan 1999 Dec 2011 95.2 85 100
Transmission Main from Kantale to Tampalakamam Trincomalee     Jan 2012 Jan 2014 1,397.80 450 80
Wadinagala/ Wan – Ela WS       Jan 2012 Dec 2015 808.5 19.04 10
Serunuwara WS Trincomalee Augmentation 9,500 Jan 2001 Dec 2013 110.1 106.28 48
Dehiattakandiya WS – Stage I & II Ampara Augmentation 16,000 Jan 2007 Dec 2012 300 250.74 99
Deyata Kirula 2013 Ampara, Trincomalee     Jan 2012 Dec 2013 1,875.00 26.89  
Northern Province
Wastewater Treatment Plant for Kilinochchi Hospital       Jan 2012 Dec 2012 36 6.95  
Mahawa/ Wariyapola/ Nikaweratiya WS       Jan 2012 Dec 2014 505 40.7 90
North Western Province
Ibbagamuwa WS       2012 Dec 2014 239 62.02 4
Divulagane WS Kurunegala New 1,950 Jan 2013 Oct 2015 46.7  
Dambadeniya       Jan 2012 Dec 2016 796 3.26 2
Mahawa/ Wariyapola/ Nikaweratiya WS Kurunegala Augmentation 45,000 Jan 2000 Dec 2014 996.7 856.31 89
Sabaragamuwa Province
Embilipitiya WS Ratnapura Augmentation 84,000 Sep  2003 Dec 2013 363 387.88 94
Pelmadulla WS Ratnapura Augmentation 14,500 Jan 2000 Dec 2015 384.2 355.47 96
Nivithigala WS Ratnapura Augmentation 14,500 Jan 1999 Dec 2013 99.1 70.01 58
Udawalawa WS Stage I & II Ratnapura Augmentation 9,400 Jan 1999 Dec 2014 973.6 654.59 90
Yatiyantota WS Kegalle Augmentation 9,400 Sep 2003 Dec 2012 165.8 176.6 85
Godakawela WS Ratnapura Augmentation 22,500 Jan 1999 Dec 2011 288.8 211.63 98
Pattampitiya WS Kegalle Extension 7,300 Jan 2001 Dec 2011 145.2 143.61 100
Galigamuwa WS Kegalle New 30,800 Jan 2011 Dec 2014 841 219.11 36
Madola WS Kegalle New 4,500 Jan 2013 Dec 2013 132  
Kiriella WS Ratnapura   7,300 Jan 2011 Dec 2014 205 21.92 97
Southern Province
Akuressa WS Matara New 15,000 Jan 1999 Dec 2011 338.6 272.66 100
Thihagoda WS Matara New 7,500 Jan  2001 Dec 2011 162.1 172.46 100
Baddegama WS Galle New 33,830 Jul 2013 Aug 2015 441    
Gonapinuwala WS Galle New 20,825 Jul 2013 Aug 2015 350    
Dikkumbura WS Galle New 17,130 Jul 2013 Aug 2015 275    
Bentota WS Galle New 18,850 Jul 2013 Aug 2015 700    
Udugama WS Galle New 6,000 Apr 2001 Dec 2011 145.5 139.51 100
Pitabeddara WS Matara New 6,000 Jan 2001 Dec 2011 130.3 102.5 98
Bonavista Kanda Area WS Matara   600 Jan 2010 Dec 2012 57 44.03 99
Hakmana WS Matara   10,000 Jan 2008 Dec 2013 383.4 123.76 60
Uva Province
Ohiya Transmission Badulla New 10,000 Feb 1999 Dec 2013 264.7 206.23 96
Monaragala WS – Stage II Monaragala New 10,000 Jun 1999 Dec 2013 154.8 142.17 98
Badalkumbura WS Monaragala New 22,000 Oct 1999 Dec 2013 124.4 97.18 86
Buttala WS Monaragala   2,600 Jan 2010 Dec 2012 295 287.44 100
Ambagasduwa WS Badulla New 6,000 Jun 1999 Dec 2013 382 137.22 72
Wellawaya WS Monaragala Augmentation 6,000 Jan 2007 Dec 2014 250 96.81 65
Western Province
Rehabilitation of Western Central WS Colombo Rehabilitation 162,500 2009 Dec 2012 1,300.00 1,317.51 97
Kirindiwela WS Gampaha New 8,000 May 1998 Dec 2013 198 172.63 90
Nittambuwa/ Veyangoda WS Gampaha Augmentation 15,000 Oct 1999 Dec 2013 210.7 201.96 96
Kalutara Integrated WS – Stage II Kalutara Augmentation 210,000 Jan 2008 Dec 2014 1,366.20 789.16 58
Jalthara – Ranala WS Colombo   17,920 Jan 2010 Dec 2013 217.2 86.15 27
Katunayake WS – Stage WS 1 & II Gampaha Augmentation 29,000 Jan 2005 Dec 2014 470 265.03 62
Kolonnawa Sewerage Colombo New 20,000     1,296.00  
Inter Provincial Projects/ Programmes
Small Schemes & Disaster Management Programme and Urgent Improvements (TCE Less than Rs.10 M )
a. Madola
b. PahalaKaduganna
c. Eheliyagoda
d. Extension to Batuwatta & Kopparamessa
e. Menikdola
f. Kabagamuwa
g. Makurakanda
h. Ellawala
    10,000 Jan 2010 Dec 2012 92.5 88.9  
Investigations, Surveys & Feasibility Studies for new project proposals           100 12.55  
Utility shiffting / replacement owing to accelerated Pradeshiya Sabha Road Development Programmmes           300 25.05