මහා පරිමාණ මලාපවහන ව්‍යාපෘති

මහා පරිමාණ මලාපවහන ව්‍යාපෘති

Project Name District Type of Project No. of Beneficiaries Duration Total Estimated Cost (Rs. million) Actual Expenditure as at end 2010 (Rs. million) Physical Progress %
From To
Central Province
Water Sector Development Project 1 Sub Project 1
Sewage disposal system for Kandy Municipal area (JICA)
Kandy New 49,700 Oct 2007 Dec 2017 22,585.00 797.99 3
Southern Province
Galle Sewerage (China) Galle     2010 2014 3,200.00  
Kataragama Sacred City Waste Water Disposal Monaragala Augmentation 15,000     615.0    
Western Province
Rehabilitation & Upgrading of Southern Catchments of GC Sewerage (Austrian) Colombo Rehabilitation 300,000 2007 2010 2,222.00 1,881.87 100
Waste Water Disposal System for Ratmalana/ Moratuwa & Ja-Ela/ Ekala Areas (SIDA) Colombo New 94,500 2008 2013 16,155.00 12,695.26 85
Greater Colombo Waste Water Managemet (ADB) Colombo Rehabilitation 500,000 2010 2014 1,012.00 36.98 2
GPOBA funded project for increasing Household Access to Sewerage Services (World Bank)       2012 2014 1,095.00 3.06  
Maharagama Boralesgamuwa (China)       2013 2015 2,200.00  
Hospital Sewerage System Improvement (China)       2012   2,100.00  
North Western Province
Greater Kurunegala Water Supply & Sanitation Kurunegala Augmentation/ New 64,000     8,283.0